Site C Employment Statistics - March 2019
Our latest employment report shows there were 3,674 workers on the Site C project in March, only 74 less than our 2018 workforce peak last September.
As we near completion of this year's clearing season for Site C, we are making some changes to our work schedule. Starting on Monday March 11, we will begin nighttime log hauling in the Cache Creek, Old Hope Road, and dam site areas.
In early December, the Site C project will start preparations for eastern reservoir clearing.
Site C will be constructed and maintained in accordance with international and Canadian safety practices to withstand major events, including unlikely extreme earthquakes and floods.