Public advisory: Delivery of a large mobile crane to Hudson's Hope
A large mobile crane is being delivered to our work area in Hudson's Hope as part of our work on the Hudson’s Hope shoreline protection berm. The crane is expected to arrive on or around Thursday, October 6, 2022.
Site C Employment Statistics - August 2022
The August 2022 employment statistics show that there were 5,396 total workers on the Site C project. Of the total workers, 3,571 were from British Columbia, or 66%. There were 1,004 workers on site from the Peace River Regional District – that’s 22% of the construction and non-construction contractor’s workforce.
Public advisory: Wood debris burning to resume on Site C project
BC Hydro will resume its burning program in Site C project areas pending suitable venting and ground conditions. Crews are clearing vegetation, where safe and practical, from the future reservoir area to help ensure boater safety and reduce impacts to dam operations.