Site C Employment Statistics – June 2021

The total project workforce number increased by 178 workers in June for a total of 5,046. This is the first time in 2021 this number is above 5,000, and our second highest worker number to date on the project. In 2020, we peaked at 5,181 on October. The total B.C. residency percentage increased by 1% to 71% in June.

Latest Information

BC Hydro to open new boat launches on Nááchę Mege reservoir
On June 26, 2026, BC Hydro will open two new public boat launches on Nááchę Mege (formerly the Site C reservoir), marking a major milestone following the safe completion of reservoir filling in fall 2024.
Site C dam receives official name: The John Horgan Dam and Generating Station
The Province and BC Hydro have announced that the Site C dam will officially be known as The John Horgan Dam and Generating Station.
BC Hydro repurposing Site C worker camp for North Coast Transmission Line Project, bringing long-term benefits to northern communities
About 85 per cent of the camp – which includes all 21 modular dormitories, the construction site office and other key supporting infrastructure – will be relocated to multiple camp locations between Prince George and Terrace.