Boaters urged to continue using caution on the Peace River near Site C
With spring weather approaching, BC Hydro is reminding the public that the section of the Peace River around the Site C dam site, upstream of the construction bridge, is permanently closed to boaters.
BC Hydro completes major milestone on Site C transmission line work
The second and final 500 kilovolt, 75 kilometre transmission line on the Site C project has been completed and energized.
Site C Employment Statistics – January 2022
Our latest employment statistics show there were 3,991 total workers on the Site C project in January 2022. Of the total workers, 2,824 were from British Columbia, or 71 per cent. There were 775 workers on site from the Peace River Regional District – that's 24 per cent of the construction and non-construction contractor's workforce.