The right bank cofferdam was in place to create a safe, dry area during construction of the buttress, powerhouse, and spillway structures. It was breached in late October and will be removed before the dam starts generating electricity. | November 2023
Media
Image
Media Name
The powerhouse and operations buildings with the 12 tailrace gate openings partially covered by the tailrace pool. | November 2023
Media
Image
Media Name
This deepened channel is a new fish habitat downstream of the dam to provide fish a safe place to feed and rest. | November 2023
Media
Image
Media Name
Final excavation and the placing large wooden structures will complete the fish habitat downstream of the dam. | November 2023
Media
Image
Media Name
Depressions in the riverbed downstream of the Site C dam will provide fish habitat when flows fluctuate during operations. | November 2023
Media
Image
Media Name
Transmission tower unit 1 rises high over the intake deck. The intake gantry crane will operate safely below the tower. | November 2023
Media
Image
Media Name
Concrete is completed on the six penstock units. Workers are installing flexible couplings, which join the lower and upper sections together to allow for movement between the two structures. | November 2023
Media
Image
Media Name
Rip rap is completed on the upstream side of the earthfill dam. The dam crest will be paved with asphalt. Work continues to complete the downstream access roads. | November 2023
Media
Image
Media Name
The Halfway River boat launch will be completed in 2024. | November 2023
Media
Image
Media Name
There will be nine transformers placed in three groups of three. Two more sets of transformer blast walls are under construction. | November 2023
Media
Image
Media Name
The approach channel is more than 96% completed. | November 2023
Media
Image
Media Name
Turbine unit 2 is 94% complete. | November 2023
Media
Image
Media Name
The stator assembly is nearing completion on generating unit 3. | November 2023
Media
Image
Media Name
The turbine runner has been installed on unit 5 and the wicket gates are being installed. | November 2023
Media
Image
Media Name
South-facing general view of Site C. | November 2023
Media
Image
Media Name
The Peace River enters the diversion inlet portal at bottom left of the completed dam. Coconut matting covered with snow is part of early reclamation work on the north bank. | November 2023
Media
Image
Media Name
Excavators continue to remove the right bank cofferdam, which was built in 2016 to create a safe, dry, construction area. | November 2023
Media
Image
Media Name
Spillway construction is completed. Installation of spillway gates continues. | November 2023
Media
Image
Media Name
With the coffer dam removed, the water from the Peace River fills the tailrace area. | November 2023
Media
Image
Media Name
The auxiliary spillway nears completion with final concrete placements. | November 2023
Media
Image
Media Name
The permanent upstream fish passage facility is approximately 75% completed. Fish moving up the Peace River to spawn will swim towards the fast water at the tailrace and enter the facility below water level. | November 2023
Media
Image
Media Name
The first of three transmission towers sits on top of one of the penstock units. | November 2023
Media
Image
Media Name
Rip rap placement is substantially completed in the upstream part of the dam, reservoir area, and approach channel. | November 2023
Media
Image
Media Name
The approach channel is substantially completed with final rip rap placement underway. | November 2023
Media
Image
Media Name
The approach channel is completed. Water will flow down the channel and enter the intakes, where trash racks have been installed. The auxiliary spillway channel is seen in the foreground. | November 2023
Media
Image
Media Name
Trash racks are installed on each of the 12 intake openings. Trash racks collect large debris and prevent it from entering the turbine units. | November 2023
Media
Image
Media Name
Final excavation and material placement will complete the fish habitat channel downstream of the dam by the end of December. | November 2023
Media
Image
Media Name
Portage Mountain Quarry will be ready for revegetation and tree planting in 2024. | November 2023
Media
Image
Media Name
The shallow water fish habitat excavation at Wilder Creek, 20 kilometres west of Fort St. John along the Peace River. | November 2023
Media
Image
Media Name
Upstream view of Site C. | November 2023
Media
Image
Media Name
A downstream side view shows Site C’s spillways, penstocks, and powerhouse and operations building. | November 2023
Media
Image
Media Name
Water will flow down the approach channel on the left and through the intake gates on the right. | November 2023
Media
Image
Media Name
Workers are dismantling the five-kilometre-long till conveyor. | November 2023
Media
Image
Media Name
As the till conveyor is dismantled, the belt is on spools where the track ends on site. | November 2023