Media
Image
Media Name
Workers are upgrading D.A. Thomas Road and building a day use area in Hudson’s Hope. | September 2023
Media
Image
Media Name
At Lynx Creek, crews are building a boat launch and day use area. | September 2023
Media
Image
Media Name
Construction is underway for the Halfway River boat launch and day use area. | September 2023
Media
Image
Media Name
Fish habitat is being developed near Wilder Creek. The reservoir will be approximately two metres deep at this location. | September 2023
Media
Image
Media Name
The Site C dam is at its full height, which is the equivalent of a 22-storey building. When the reservoir is filled, the dam will direct water to the approach channel. | September 2023
Media
Image
Media Name
Excavators have started removing the right bank coffer dam as work on the spillways and tailrace nears completion. | September 2023
Media
Image
Media Name
Water will go through six penstocks into the powerhouse, then exit through the tailrace. The spillways on the left will safely pass flows from the reservoir. | September 2023
Media
Image
Media Name
Crews are finishing concrete placement for the tailrace erosion protection slabs. Workers are also excavating the interior of the right bank cofferdam and placing riprap. | September 2023
Media
Image
Media Name
When the Site C reservoir is filled, water will flow down the approach channel and enter through the intakes. | September 2023
Media
Image
Media Name
Rip rap is one of the many protective layers in the approach channel where water will flow from the reservoir into the intakes. | September 2023
Media
Image
Media Name
Turbine unit 1 is close to completion in the powerhouse. | September 2023
Media
Image
Media Name
Turbine units 2 through 6 in the powerhouse are at varying stages of completion. | September 2023
Media
Image
Media Name
Work on turbine unit 2 is ongoing with the installation of the bottom ring runner and turbine shaft, and stator stacking. | September 2023
Media
Image
Media Name
The second-stage concrete has been poured on turbine unit 4. Next is installation of the stator frame. | September 2023
Media
Image
Media Name
Water will flow inside this spiral case and spin a turbine to generate electricity. | September 2023
Media
Image
Media Name
The lower section of turbine unit 1, which is nearing completion. | September 2023
Media
Image
Media Name
These two sections will be connected to allow water to flow from a penstock unit on the right into a turbine unit on the left. | September 2023
Media
Image
Media Name
As water leaves the powerhouse on the left, it enters the tailrace where it is slowed before being directed downstream to continue the river flow. | September 2023
Media
Image
Media Name
The first of three sets of transformers are on their foundations. They need to be filled with oil before commissioning starts. | September 2023
Media
Image
Media Name
The first of nine transformers is being assembled in the transformer yard. | September 2023
Media
Image
Media Name
When the reservoir is filled, the earthfill dam (at centre) will direct water to the approach channel on the right. | September 2023
Media
Image
Media Name
Water will flow down the approach channel on the left and through the intake gates to the right. | September 2023
Media
Image
Media Name
This new fish habitat is being constructed in a side channel downstream of the dam. | September 2023
Media
Image
Media Name
A fish habitat channel downstream of the dam is deep to prevent fish getting stranded in low water. There are structures placed along the channel where fish can feed and rest. | September 2023
Media
Image
Media Name
On the upstream side of the generating station, water flows from the approach channel into the six intake units. | September 2023
Media
Image
Media Name
Trash racks are installed at the inlet portals on units 1 to 3. These screens protect the turbine units by stopping debris from entering the intakes. | September 2023
Media
Image
Media Name
A waterproof liner is installed on the buttress wall. | September 2023
Media
Image
Media Name
A boat access ramp is being constructed on the downstream side of the earth fill dam. | September 2023
Media
Image
Media Name
A downstream side view shows Site C’s spillways, penstocks, powerhouse, and tailrace. | September 2023
Media
Image
Media Name
Site C has two mechanical spillways and an auxiliary spillway to safely pass flows from the reservoir. The right bank cofferdam in front will be removed when the dam is in operation. | September 2023
Media
Image
Media Name
Tailrace construction is nearing completion. | September 2023
Media
Image
Media Name
The permanent fish passage at the west end of the tailrace wall will allow fish to migrate upstream and fulfil portions of their lifecycles. | September 2023
Media
Image
Media Name
The blue draft tube maintenance gates close the tailrace with a watertight seal for maintenance. | September 2023
Order
4.00