Media
Image
![Two cranes lift and install an air receiver tank. The tank stores pressurized air to run different types of equipment. | April 2023](/sites/default/files/styles/large/public/2023-06/01-STC_EVVP2037_20230405-x1500.jpg?itok=dMHnliiR)
Media Name
Two cranes lift and install an air receiver tank. The tank stores pressurized air to run different types of equipment. | April 2023
Caption
Two cranes lift and install an air receiver tank. The tank stores pressurized air to run different types of equipment. | April 2023
Media
Image
![A worker guides the air receiver tank as it’s lowered into position below the powerhouse floor. | April 2023](/sites/default/files/styles/large/public/2023-06/02-STC_EVVP2081_20230405-x1500.jpg?itok=kFmkbiej)
Media Name
A worker guides the air receiver tank as it’s lowered into position below the powerhouse floor. | April 2023
Caption
A worker guides the air receiver tank as it’s lowered into position below the powerhouse floor. | April 2023
Media
Image
![Work continues on the approach channel. | April 2023](/sites/default/files/styles/large/public/2023-06/03-STC_0V2A0135_20230427-x1500.jpg?itok=ZBVKMraW)
Media Name
Work continues on the approach channel. | April 2023
Caption
Work continues on the approach channel. | April 2023
Media
Image
![Crews clean the bedrock layer before placing concrete in the approach channel. | April 2023](/sites/default/files/styles/large/public/2023-06/04-STC_0V2A0245-Pano_20230427-x1500.jpg?itok=IPZ2Szdf)
Media Name
Crews clean the bedrock layer before placing concrete in the approach channel. | April 2023
Caption
Crews clean the bedrock layer before placing concrete in the approach channel. | April 2023
Media
Image
![The initial concrete curing of the roller compacted concrete buttress is complete. We’re removing the insulating panels to patch and finish the concrete. | April 2023](/sites/default/files/styles/large/public/2023-06/05-STC_0V2A0207_20230427-x1500.jpg?itok=_yrgGQIB)
Media Name
The initial concrete curing of the roller compacted concrete buttress is complete. We’re removing the insulating panels to patch and finish the concrete. | April 2023
Caption
The initial concrete curing of the roller compacted concrete buttress is complete. We’re removing the insulating panels to patch and finish the concrete. | April 2023
Media
Image
![A waterproof membrane is being installed in the approach channel. | April 2023](/sites/default/files/styles/large/public/2023-06/06-STC_0V2A0218_20230427-x1500.jpg?itok=ZyfFTYgK)
Media Name
A waterproof membrane is being installed in the approach channel. | April 2023
Caption
A waterproof membrane is being installed in the approach channel. | April 2023
Media
Image
![A partially completed section of the approach channel lining, with riprap cover and granular fill. | April 2023](/sites/default/files/styles/large/public/2023-06/07-STC_0V2A0137_20230427-x1500.jpg?itok=4en5Ejyc)
Media Name
A partially completed section of the approach channel lining, with riprap cover and granular fill. | April 2023
Caption
A partially completed section of the approach channel lining, with riprap cover and granular fill. | April 2023
Media
Image
![The centre wall, which divides the approach channel in two, is nearly complete. | April 2023](/sites/default/files/styles/large/public/2023-06/08-STC_0V2A0504_20230427-x1500.jpg?itok=SsCDRRjq)
Media Name
The centre wall, which divides the approach channel in two, is nearly complete. | April 2023
Caption
The centre wall, which divides the approach channel in two, is nearly complete. | April 2023
Media
Image
![Crews place reinforcing steel for the centre wall in the approach channel. | April 2023](/sites/default/files/styles/large/public/2023-06/09-STC_0V2A0398_20230427-x1500.jpg?itok=1lJSMH0S)
Media Name
Crews place reinforcing steel for the centre wall in the approach channel. | April 2023
Caption
Crews place reinforcing steel for the centre wall in the approach channel. | April 2023
Media
Image
![Concrete is placed on the passive spillway, which operates without power and safely passes water that would otherwise go through the mechanical spillways. | April 2023](/sites/default/files/styles/large/public/2023-06/10-STC_0V2A0379_20230427-x1500.jpg?itok=9BVrIg8L)
Media Name
Concrete is placed on the passive spillway, which operates without power and safely passes water that would otherwise go through the mechanical spillways. | April 2023
Caption
Concrete is placed on the passive spillway, which operates without power and safely passes water that would otherwise go through the mechanical spillways. | April 2023
Media
Image
![The guides for the trash racks are installed behind the white hoardings. Trash racks stop large debris from entering the intakes. | April 2023](/sites/default/files/styles/large/public/2023-06/11-STC_0V2A0321_20230427-x1500.jpg?itok=ee2CiQw4)
Media Name
The guides for the trash racks are installed behind the white hoardings. Trash racks stop large debris from entering the intakes. | April 2023
Caption
The guides for the trash racks are installed behind the white hoardings. Trash racks stop large debris from entering the intakes. | April 2023
Media
Image
![An operating gate is on the intake platform below the intake gantry crane. Each of the six intake units will have a gate that will be raised and lowered by the gantry crane. | April 2023](/sites/default/files/styles/large/public/2023-06/12-STC_0V2A0428_20230427-x1500.jpg?itok=5RzvmMND)
Media Name
An operating gate is on the intake platform below the intake gantry crane. Each of the six intake units will have a gate that will be raised and lowered by the gantry crane. | April 2023
Caption
An operating gate is on the intake platform below the intake gantry crane. Each of the six intake units will have a gate that will be raised and lowered by the gantry crane. | April 2023
Media
Image
![Concrete blast walls are built behind the powerhouse to enclose the three transformers. | April 2023](/sites/default/files/styles/large/public/2023-06/13-STC_0V2A0417_20230427-x1500.jpg?itok=fmqvnaZZ)
Media Name
Concrete blast walls are built behind the powerhouse to enclose the three transformers. | April 2023
Caption
Concrete blast walls are built behind the powerhouse to enclose the three transformers. | April 2023
Media
Image
![The first concrete lift is complete to close the east spilling basin weir. The weir slows the energy from water that flows from the spillways. | April 2023](/sites/default/files/styles/large/public/2023-06/14-STC_0V2A0384_20230427-x1500.jpg?itok=0eKCMV9K)
Media Name
The first concrete lift is complete to close the east spilling basin weir. The weir slows the energy from water that flows from the spillways. | April 2023
Caption
The first concrete lift is complete to close the east spilling basin weir. The weir slows the energy from water that flows from the spillways. | April 2023
Media
Image
![North-facing view across the earthfill dam. | April 2023](/sites/default/files/styles/large/public/2023-06/15-STC_0V2A0481_20230427-x1500.jpg?itok=pgWRauHa)
Media Name
North-facing view across the earthfill dam. | April 2023
Caption
North-facing view across the earthfill dam. | April 2023
Media
Image
![Turbine runner shaft installation in unit 2. | April 2023](/sites/default/files/styles/large/public/2023-06/16-STC_0V2A0779_20230428-x1500.jpg?itok=kbt-tPIS)
Media Name
Turbine runner shaft installation in unit 2. | April 2023
Caption
Turbine runner shaft installation in unit 2. | April 2023
Media
Image
![Work continues in the powerhouse. | April 2023](/sites/default/files/styles/large/public/2023-06/17-STC_0V2A0747_20230428-x1500.jpg?itok=mKKCio-P)
Media Name
Work continues in the powerhouse. | April 2023
Caption
Work continues in the powerhouse. | April 2023
Media
Image
![Concrete placement is complete on all six penstock units. | April 2023](/sites/default/files/styles/large/public/2023-06/18-STC_0V2A0741_20230428-x1500.jpg?itok=fP7F4nD0)
Media Name
Concrete placement is complete on all six penstock units. | April 2023
Caption
Concrete placement is complete on all six penstock units. | April 2023
Media
Image
![A worker uses a laser alignment system to place cables around a junction box. | April 2023](/sites/default/files/styles/large/public/2023-06/19-STC_0V2A0704_20230428-x1500.jpg?itok=-b93cN9b)
Media Name
A worker uses a laser alignment system to place cables around a junction box. | April 2023
Caption
A worker uses a laser alignment system to place cables around a junction box. | April 2023
Order
9.00