Media
Image
![The unit 2 and 3 trash rack guides are under the winter hoardings and work continues to complete intake units 4 and 5. | March 2023](/sites/default/files/styles/large/public/2023-03/01-STC_EVVP9904_20230301-x1500.jpg?itok=E6MwcRiv)
Media Name
The unit 2 and 3 trash rack guides are under the winter hoardings and work continues to complete intake units 4 and 5. | March 2023
Caption
The unit 2 and 3 trash rack guides are under the winter hoardings and work continues to complete intake units 4 and 5. | March 2023
Media
Image
![Installing rebar on the approach channel wall for pouring concrete. | March 2023](/sites/default/files/styles/large/public/2023-03/02-STC_EVVP9972_20230301-x1500.jpg?itok=6iSXZPbz)
Media Name
Installing rebar on the approach channel wall for pouring concrete. | March 2023
Caption
Installing rebar on the approach channel wall for pouring concrete. | March 2023
Media
Image
![After concrete is poured, the approach channel wall is covered with winter hoardings to allow concrete to cure. | March 2023](/sites/default/files/styles/large/public/2023-03/03-STC_EVVP9926_20230301-x1500.jpg?itok=8qo8Jr_i)
Media Name
After concrete is poured, the approach channel wall is covered with winter hoardings to allow concrete to cure. | March 2023
Caption
After concrete is poured, the approach channel wall is covered with winter hoardings to allow concrete to cure. | March 2023
Media
Image
![Workers regularly climb the 17-storey staircase at the centre block of the spillway headworks. | March 2023](/sites/default/files/styles/large/public/2023-03/04-STC_EVVP9997_20230301-x1500.jpg?itok=dMcUfyjc)
Media Name
Workers regularly climb the 17-storey staircase at the centre block of the spillway headworks. | March 2023
Caption
Workers regularly climb the 17-storey staircase at the centre block of the spillway headworks. | March 2023
Media
Image
![Installing the formwork to pour concrete on the west end of the approach channel wall. | March 2023](/sites/default/files/styles/large/public/2023-03/05-STC_EVVP9950_20230301-x1500.jpg?itok=PWCRYN-J)
Media Name
Installing the formwork to pour concrete on the west end of the approach channel wall. | March 2023
Caption
Installing the formwork to pour concrete on the west end of the approach channel wall. | March 2023
Media
Image
![Workers build an access walkway in advance of the next concrete pour for the auxiliary spillway. | March 2023](/sites/default/files/styles/large/public/2023-03/06-STC_EVVP0528_20230302-x1500.jpg?itok=FYZyOj6Z)
Media Name
Workers build an access walkway in advance of the next concrete pour for the auxiliary spillway. | March 2023
Caption
Workers build an access walkway in advance of the next concrete pour for the auxiliary spillway. | March 2023
Media
Image
![The end wall of the auxiliary spillway as it transitions into the slurry wall. This is a trench filled with a concrete mix and rebar (slurry) down to bedrock to prevent water seepage. | March 2023](/sites/default/files/styles/large/public/2023-03/07-STC_EVVP0554_20230302-x1500.jpg?itok=aS_iFlSY)
Media Name
The end wall of the auxiliary spillway as it transitions into the slurry wall. This is a trench filled with a concrete mix and rebar (slurry) down to bedrock to prevent water seepage. | March 2023
Caption
The end wall of the auxiliary spillway as it transitions into the slurry wall. This is a trench filled with a concrete mix and rebar (slurry) down to bedrock to prevent water seepage. | March 2023
Media
Image
![Installing reinforcing steel on the auxiliary spillway. | March 2023](/sites/default/files/styles/large/public/2023-03/08-STC_EVVP0564_20230302-x1500.jpg?itok=LlYmJyzS)
Media Name
Installing reinforcing steel on the auxiliary spillway. | March 2023
Caption
Installing reinforcing steel on the auxiliary spillway. | March 2023
Media
Image
![Levelling of the zone 8 material on the upstream shell of the dam. | March 2023](/sites/default/files/styles/large/public/2023-03/09-STC_EVVP0461_20230302-x1500.jpg?itok=-tk3V-3F)
Media Name
Levelling of the zone 8 material on the upstream shell of the dam. | March 2023
Caption
Levelling of the zone 8 material on the upstream shell of the dam. | March 2023
Media
Image
![Working on the permanent debris boom. | March 2023](/sites/default/files/styles/large/public/2023-03/10-STC_EVVP0466_20230302-x1500.jpg?itok=JqPKtGrq)
Media Name
Working on the permanent debris boom. | March 2023
Caption
Working on the permanent debris boom. | March 2023
Media
Image
![Where the Moberly and Peace rivers meet upstream of the dam, the debris boom can be seen, along with the inlet portal where the river flows around the dam. | March 2023](/sites/default/files/styles/large/public/2023-03/11-STC_0303_TRE_R5A_DJI_0087_20230303-x1500.jpg?itok=PgCwhV6G)
Media Name
Where the Moberly and Peace rivers meet upstream of the dam, the debris boom can be seen, along with the inlet portal where the river flows around the dam. | March 2023
Caption
Where the Moberly and Peace rivers meet upstream of the dam, the debris boom can be seen, along with the inlet portal where the river flows around the dam. | March 2023
Media
Image
![The spillway basin below the auxiliary spillway. | March 2023](/sites/default/files/styles/large/public/2023-03/12-STC_EVVP0760_20230306-x1500.jpg?itok=6qxpKSu0)
Media Name
The spillway basin below the auxiliary spillway. | March 2023
Caption
The spillway basin below the auxiliary spillway. | March 2023
Media
Image
![Installing reinforcing steel and formwork to pour concrete on penstock unit 5. Water will flow through six penstocks into the powerhouse to generate electricity. | March 2023](/sites/default/files/styles/large/public/2023-03/13-STC_EVVP0829_20230306-x1500.jpg?itok=oFoM_zWe)
Media Name
Installing reinforcing steel and formwork to pour concrete on penstock unit 5. Water will flow through six penstocks into the powerhouse to generate electricity. | March 2023
Caption
Installing reinforcing steel and formwork to pour concrete on penstock unit 5. Water will flow through six penstocks into the powerhouse to generate electricity. | March 2023
Media
Image
![This gantry crane lifts the intake gates. It is on rails to allow movement between intake units 1 through 6. | March 2023](/sites/default/files/styles/large/public/2023-03/14-STC_EVVP0853_20230306-x1500.jpg?itok=0zvDU--T)
Media Name
This gantry crane lifts the intake gates. It is on rails to allow movement between intake units 1 through 6. | March 2023
Caption
This gantry crane lifts the intake gates. It is on rails to allow movement between intake units 1 through 6. | March 2023
Media
Image
![Equipment is brought to the main service bay in the powerhouse to be used for installation. | March 2023](/sites/default/files/styles/large/public/2023-03/15-STC_EVVP0961_20230310-x1500.jpg?itok=xmmoRLYo)
Media Name
Equipment is brought to the main service bay in the powerhouse to be used for installation. | March 2023
Caption
Equipment is brought to the main service bay in the powerhouse to be used for installation. | March 2023
Media
Image
![The centre section of unit 3 rotor assembly is in the main service bay of the powerhouse ahead of installation. | March 2023](/sites/default/files/styles/large/public/2023-03/16-STC_EVVP0968_20230310-x1500.jpg?itok=ZtS_ciic)
Media Name
The centre section of unit 3 rotor assembly is in the main service bay of the powerhouse ahead of installation. | March 2023
Caption
The centre section of unit 3 rotor assembly is in the main service bay of the powerhouse ahead of installation. | March 2023
Media
Image
![The asphalt and sub-base gravel from the original section of Farrell Creek on Highway 29 has been broken and hauled away to be ground and re-used in future road construction. | March 2023](/sites/default/files/styles/large/public/2023-03/17-STC_0309_HWY_DRY_FARREL_DJI_0588_20230309-x1500.jpg?itok=GOE3fn88)
Media Name
The asphalt and sub-base gravel from the original section of Farrell Creek on Highway 29 has been broken and hauled away to be ground and re-used in future road construction. | March 2023
Caption
The asphalt and sub-base gravel from the original section of Farrell Creek on Highway 29 has been broken and hauled away to be ground and re-used in future road construction. | March 2023
Media
Image
![South-facing view of the Farrell Creek bridge on Highway 29 where the original highway section has been removed and coarse woody debris will be spread. | March 2023](/sites/default/files/styles/large/public/2023-03/18-STC_0309_HWY_DRY_FARREL_DJI_0583_20230309-x1500.jpg?itok=l1I0rYcN)
Media Name
South-facing view of the Farrell Creek bridge on Highway 29 where the original highway section has been removed and coarse woody debris will be spread. | March 2023
Caption
South-facing view of the Farrell Creek bridge on Highway 29 where the original highway section has been removed and coarse woody debris will be spread. | March 2023
Media
Image
![Water from the Peace River will flow down the approach channel on the far right and exit the Site C dam downstream. | March 2023](/sites/default/files/styles/large/public/2023-05/001-APCH_GSS_R5B_MMR_EV_0323_R5b_Core_A24_GSSDJI_0146_202303231500x.jpg?itok=54n2o8th)
Media Name
Water from the Peace River will flow down the approach channel on the far right and exit the Site C dam downstream. | March 2023
Caption
Water from the Peace River will flow down the approach channel on the far right and exit the Site C dam downstream. | March 2023
Media
Image
![Construction of the approach channel wall. | March 2023](/sites/default/files/styles/large/public/2023-05/002-APCH_GSS_R5B_MMR_EV_0323_R5b_Core_A24_GSSDJI_0154_202303231500x.jpg?itok=gsAEKAAx)
Media Name
Construction of the approach channel wall. | March 2023
Caption
Construction of the approach channel wall. | March 2023
Media
Image
![Water will flow through these six penstocks down into the powerhouse, where it will turn the turbines to make electricity. | March 2023](/sites/default/files/styles/large/public/2023-05/003-APCH_GSS_R5B_MMR_EV_0323_R5b_Core_A24_GSSDJI_0185_202303231500x.jpg?itok=S8ua_vE6)
Media Name
Water will flow through these six penstocks down into the powerhouse, where it will turn the turbines to make electricity. | March 2023
Caption
Water will flow through these six penstocks down into the powerhouse, where it will turn the turbines to make electricity. | March 2023
Media
Image
![Water will flow down the approach channel (left) and down through the six penstocks (centre) into the generating station. | March 2023](/sites/default/files/styles/large/public/2023-05/004-APCH_GSS_R5B_MMR_EV_0323_R5b_Core_A24_GSSDJI_0192_202303231500x.jpg?itok=kQ60CS8c)
Media Name
Water will flow down the approach channel (left) and down through the six penstocks (centre) into the generating station. | March 2023
Caption
Water will flow down the approach channel (left) and down through the six penstocks (centre) into the generating station. | March 2023
Media
Image
![A downstream view of the approach channel. | March 2023](/sites/default/files/styles/large/public/2023-05/005-APCH_GSS_R5B_MMR_EV_0323_R5b_Core_A24_GSSDJI_0209-Pano_202303231500x.jpg?itok=EUA92eU-)
Media Name
A downstream view of the approach channel. | March 2023
Caption
A downstream view of the approach channel. | March 2023
Media
Image
![The spillways are an important safety feature, as they allow the passage of large volumes of water from the reservoir into the river channel downstream. | March 2023](/sites/default/files/styles/large/public/2023-05/006-APCH_GSS_R5B_MMR_EV_0323_R5b_Core_A24_GSSDJI_0228_202303231500x.jpg?itok=jtNmwhQX)
Media Name
The spillways are an important safety feature, as they allow the passage of large volumes of water from the reservoir into the river channel downstream. | March 2023
Caption
The spillways are an important safety feature, as they allow the passage of large volumes of water from the reservoir into the river channel downstream. | March 2023
Media
Image
![At the permanent upstream fish passage, migrating fish will be sorted, tagged, and released past the dam site. | March 2023](/sites/default/files/styles/large/public/2023-05/007-APCH_GSS_R5B_MMR_EV_0323_R5b_Core_A24_GSSDJI_0242_202303231500x.jpg?itok=UZGXmjcV)
Media Name
At the permanent upstream fish passage, migrating fish will be sorted, tagged, and released past the dam site. | March 2023
Caption
At the permanent upstream fish passage, migrating fish will be sorted, tagged, and released past the dam site. | March 2023
Media
Image
![Water will exit the generating station to the tailrace and flow downstream. At left, construction is underway on the spillways. | March 2023](/sites/default/files/styles/large/public/2023-05/008-APCH_GSS_R5B_MMR_EV_0323_R5b_Core_A24_GSSDJI_0259_202303231500x.jpg?itok=DWgTb4h4)
Media Name
Water will exit the generating station to the tailrace and flow downstream. At left, construction is underway on the spillways. | March 2023
Caption
Water will exit the generating station to the tailrace and flow downstream. At left, construction is underway on the spillways. | March 2023
Media
Image
![There are six turbine generator units inside the powerhouse. Unit 1 is in the foreground, where the upper bracket is installed. | March 2023](/sites/default/files/styles/large/public/2023-05/009-PWH_TAL_PUFOS_EV_EVVP1354_202303201500x.jpg?itok=PX8bdZ8a)
Media Name
There are six turbine generator units inside the powerhouse. Unit 1 is in the foreground, where the upper bracket is installed. | March 2023
Caption
There are six turbine generator units inside the powerhouse. Unit 1 is in the foreground, where the upper bracket is installed. | March 2023
Media
Image
![The stator bar is installed for the Unit 2 generator inside the powerhouse. The stator converts the rotating magnetic field into an electrical current. | March 2023](/sites/default/files/styles/large/public/2023-05/010-PWH_TAL_PUFOS_EV_EVVP1360_202303201500x.jpg?itok=SEMl_Tyt)
Media Name
The stator bar is installed for the Unit 2 generator inside the powerhouse. The stator converts the rotating magnetic field into an electrical current. | March 2023
Caption
The stator bar is installed for the Unit 2 generator inside the powerhouse. The stator converts the rotating magnetic field into an electrical current. | March 2023
Media
Image
![Workers connect a crane to lift the second turbine runner. There will be six turbine runners, each weighing about 165,000 kilograms. | March 2023](/sites/default/files/styles/large/public/2023-05/011-STC_EVVP1397_202303281500x.jpg?itok=i9T8T7D5)
Media Name
Workers connect a crane to lift the second turbine runner. There will be six turbine runners, each weighing about 165,000 kilograms. | March 2023
Caption
Workers connect a crane to lift the second turbine runner. There will be six turbine runners, each weighing about 165,000 kilograms. | March 2023
Media
Image
![A crane is connected to a lifting device to install the second turbine runner. The runner is the heaviest single project component. | March 2023](/sites/default/files/styles/large/public/2023-05/012-STC_EVVP1422_202303281500x.jpg?itok=zXALjSew)
Media Name
A crane is connected to a lifting device to install the second turbine runner. The runner is the heaviest single project component. | March 2023
Caption
A crane is connected to a lifting device to install the second turbine runner. The runner is the heaviest single project component. | March 2023
Order
10.00