Media
Image
Media Name
Fish travelling upstream to spawn will be sorted in the permanent upstream fish passage. Fish will be sorted, tagged, and released into the reservoir. | February 2023
Media
Image
Media Name
The transmission structure on top of the powerhouse will connect the transformers below to the transmission towers on top of the intake structure. Those towers will then feed electricity to the substation. | February 2023
Media
Image
Media Name
Water will flow from the approach channel into the six intake gates. It will then travel down the penstocks into the turbine units to generate electricity. | February 2023
Media
Image
Media Name
The unit 1 stator winding is completed. Thrust bearing assembly can be seen on the lower bracket. | February 2023
Media
Image
Media Name
Unit 2 stator core is prepared to install the winding. | February 2023
Media
Image
Media Name
Unit 3 generator enclosure and turbine pit is prepared for installation of the turbine and generator components. | February 2023
Media
Image
Media Name
Upstream view of the dam site. | February 2023
Media
Image
Media Name
East-facing over the approach channel where water will flow from the reservoir through the intakes into the powerhouse to generate electricity. | February 2023
Media
Image
Media Name
Construction of the approach channel wall. | February 2023
Media
Image
Media Name
Touch-up painting the unit 1 rotor after final assembly. | February 2023
Media
Image
Media Name
Connecting the unit 1 thrust block onto turbine shaft. | February 2023
Media
Image
Media Name
Preparing unit 2 stator core to install the windings. | February 2023
Media
Image
Media Name
The unit 2 turbine pit is shown with the bottom ring and stay ring installed. | February 2023
Media
Image
Media Name
The governor hydraulic power unit accumulator tank is the source of power to open and close the wicket gates. | February 2023
Media
Image
Media Name
The unit 1 rotor is installed in the lifting device. | February 2023
Media
Image
Media Name
Unit 1 rotor and the tandem lifting beam are ready to lift the rotor with the crane. | February 2023
Media
Image
Media Name
During the Unit 1 rotor lift, it is moved over the generator pit to be lowered into position. | February 2023
Media
Image
Media Name
The first turbine rotor is placed into the generator pit inside the powerhouse. | February 2023
Order
11.00