Phase 1 of the P6 reclamation work was completed in mid-January. The island’s original soil has been spread over the disturbed areas to allow for growth of seedlings which will be planted in the spring of 2024. | January 2023
Caption
Phase 1 of the P6 reclamation work was completed in mid-January. The island’s original soil has been spread over the disturbed areas to allow for growth of seedlings which will be planted in the spring of 2024. | January 2023
Media
Image

Media Name
Unit 1 is in the background with the unit’s lower bracket in the foreground, where the generation bearing is being installed. | January 2023
Caption
Unit 1 is in the background with the unit’s lower bracket in the foreground, where the generation bearing is being installed. | January 2023
Media
Image

Media Name
Assembly of the rotors for units 1 and 2. | January 2023
Caption
Assembly of the rotors for units 1 and 2. | January 2023
Media
Image

Media Name
Unit 1 stator winding and the turbine assembly. | January 2023
Caption
Unit 1 stator winding and the turbine assembly. | January 2023
Media
Image

Media Name
Brazing the unit 1 stator winding. This is the process of joining copper bars in the stator winding together. | January 2023
Caption
Brazing the unit 1 stator winding. This is the process of joining copper bars in the stator winding together. | January 2023
Media
Image

Media Name
Unit 1 spiral case showing the stay vanes which guide the water to the runner blades, and the wicket gates which adjust the flow of water to the turbine. | January 2023
Caption
Unit 1 spiral case showing the stay vanes which guide the water to the runner blades, and the wicket gates which adjust the flow of water to the turbine. | January 2023
Media
Image

Media Name
Assembling the unit 2 stator core and machining the stay ring flanges. The stator core helps transfer the magnetic field from the rotor into the winding. | January 2023
Caption
Assembling the unit 2 stator core and machining the stay ring flanges. The stator core helps transfer the magnetic field from the rotor into the winding. | January 2023
Media
Image

Media Name
Unit 6 spiral case is prepared for a pressure test. | January 2023
Caption
Unit 6 spiral case is prepared for a pressure test. | January 2023
Media
Image

Media Name
The worker accommodation camp on the north bank houses approximately 2,000 workers. | January 2023
Caption
The worker accommodation camp on the north bank houses approximately 2,000 workers. | January 2023
Media
Image

Media Name
The upstream wall of the passive spillway (foreground) where water enters the spillway. | January 2023
Caption
The upstream wall of the passive spillway (foreground) where water enters the spillway. | January 2023
Media
Image

Media Name
Assembly of the permanent gantry crane, used for heavy lifts, on top of one of the intake units. | January 2023
Caption
Assembly of the permanent gantry crane, used for heavy lifts, on top of one of the intake units. | January 2023
Media
Image

Media Name
The approach channel and upstream face of the buttress, intakes, and spillways. | January 2023
Caption
The approach channel and upstream face of the buttress, intakes, and spillways. | January 2023
Media
Image

Media Name
Crews work on the interior wall of the passive spillway (at right), which is like an overflow spillway. Under the orange tarps at centre, crews install the second spillway operating gate. | January 2023
Caption
Crews work on the interior wall of the passive spillway (at right), which is like an overflow spillway. Under the orange tarps at centre, crews install the second spillway operating gate. | January 2023
Media
Image

Media Name
Under the heated tarps, concrete is curing for the centre wall of approach channel. Further back, crews install formwork and reinforce steel. | January 2023
Caption
Under the heated tarps, concrete is curing for the centre wall of approach channel. Further back, crews install formwork and reinforce steel. | January 2023
Media
Image

Media Name
Spillways, powerhouse and generating station construction continues. | January 2023
Caption
Spillways, powerhouse and generating station construction continues. | January 2023
Media
Image

Media Name
Formworks are being built to encase the penstocks in concrete. | January 2023
Caption
Formworks are being built to encase the penstocks in concrete. | January 2023