Media
Image
![Panoramic shot of the construction. | November 2022](/sites/default/files/styles/large/public/2022-12/01-AFDE_SITE221101-1500x_0.jpg?itok=gZRCv79E)
Media Name
From left: The six intake gates, where water enters the powerhouse, and spillway upper headworks, where extra water is passed through. | November 2022
Caption
From left: The six intake gates, where water enters the powerhouse, and spillway upper headworks, where extra water is passed through. | November 2022
Media
Image
![Gate guides for the radial and maintenance gates, which lift and allow water to flow into the spillway. | November 2022](/sites/default/files/styles/large/public/2022-12/02-AFDE_SITE221101-104-1500x.jpg?itok=xO1hJtD-)
Media Name
Gate guides for the radial and maintenance gates, which lift and allow water to flow into the spillway. | November 2022
Caption
Gate guides for the radial and maintenance gates, which lift and allow water to flow into the spillway. | November 2022
Media
Image
![Workers use a swing stage to patch and finish concrete on a spillway training wall. | November 2022](/sites/default/files/styles/large/public/2022-12/03-AFDE_SITE221101-49-1500x.jpg?itok=h-Hx0Sti)
Media Name
Workers use a swing stage to patch and finish concrete on a spillway training wall. | November 2022
Caption
Workers use a swing stage to patch and finish concrete on a spillway training wall. | November 2022
Media
Image
![Panorama of the spillways, stilling basin weirs, and 12 tailrace galleries, where water flows out of the powerhouse. | November 2022](/sites/default/files/styles/large/public/2022-12/04-AFDE_SITE221101-105-1500x.jpg?itok=TamoDnu8)
Media Name
Panorama of the spillways, stilling basin weirs, and 12 tailrace galleries, where water flows out of the powerhouse. | November 2022
Caption
Panorama of the spillways, stilling basin weirs, and 12 tailrace galleries, where water flows out of the powerhouse. | November 2022
Media
Image
![From left: the auxiliary spillway, the three spillway operating gates, six low-level operating gates, and the stilling basin weir in front. | November 2022](/sites/default/files/styles/large/public/2022-12/05-AFDE_SITE221101-117-1500x.jpg?itok=m4Hajme_)
Media Name
From left: the auxiliary spillway, the three spillway operating gates, six low-level operating gates, and the stilling basin weir in front. | November 2022
Caption
From left: the auxiliary spillway, the three spillway operating gates, six low-level operating gates, and the stilling basin weir in front. | November 2022
Media
Image
![Hoarding and heating (under the plastic sheeting) to protect from the cold while pouring concrete at the penstocks. | November 2022](/sites/default/files/styles/large/public/2022-12/06-AFDE_SITE221101-92-1500x.jpg?itok=bXIx2sud)
Media Name
Hoarding and heating (under the plastic sheeting) to protect from the cold while pouring concrete at the penstocks. | November 2022
Caption
Hoarding and heating (under the plastic sheeting) to protect from the cold while pouring concrete at the penstocks. | November 2022
Media
Image
![Welding the tailrace foundation piles, which adds stability to the tailrace area behind the powerhouse. | November 2022](/sites/default/files/styles/large/public/2022-12/07-AFDE_SITE221101-174-1500x.jpg?itok=JDoet6kc)
Media Name
Welding the tailrace foundation piles, which adds stability to the tailrace area behind the powerhouse. | November 2022
Caption
Welding the tailrace foundation piles, which adds stability to the tailrace area behind the powerhouse. | November 2022
Media
Image
![Concrete is poured into the tailrace pile caps (under the tarps), which are then covered to allow the concrete to cure. | November 2022](/sites/default/files/styles/large/public/2022-12/08-AFDE_SITE221101-185-1500x.jpg?itok=cotPG51n)
Media Name
Concrete is poured into the tailrace pile caps (under the tarps), which are then covered to allow the concrete to cure. | November 2022
Caption
Concrete is poured into the tailrace pile caps (under the tarps), which are then covered to allow the concrete to cure. | November 2022
Media
Image
![Permanent upstream fish passage facility, which allows fish to migrate upstream past the dam. | November 2022](/sites/default/files/styles/large/public/2022-12/09-AFDE_SITE221101-177-1500x.jpg?itok=iQzh9KXj)
Media Name
Permanent upstream fish passage facility, which allows fish to migrate upstream past the dam. | November 2022
Caption
Permanent upstream fish passage facility, which allows fish to migrate upstream past the dam. | November 2022
Media
Image
![Panorama of the approach channel with the buttress, intakes, and spillways. | November 2022](/sites/default/files/styles/large/public/2022-12/010-STC_EV_1102_PWH_APP_DJI_0914-Pano_20221102-1500x.jpg?itok=7alRdBCM)
Media Name
Panorama of the approach channel with the buttress, intakes, and spillways. | November 2022
Caption
Panorama of the approach channel with the buttress, intakes, and spillways. | November 2022
Media
Image
![West-facing view of the approach channel centre wall, where water approaches from behind the powerhouse. | November 2022](/sites/default/files/styles/large/public/2022-12/011-STC_EV_1102_PWH_APP_DJI_0909_20221102-1500x.jpg?itok=nfKe0rLh)
Media Name
West-facing view of the approach channel centre wall, where water approaches from behind the powerhouse. | November 2022
Caption
West-facing view of the approach channel centre wall, where water approaches from behind the powerhouse. | November 2022
Media
Image
![Intake unit 4 is prepared for concrete pour. | November 2022](/sites/default/files/styles/large/public/2022-12/012-STC_EV_EVVP1474_20221102-1500x.jpg?itok=vZprlNg9)
Media Name
Intake unit 4 is prepared for concrete pour. | November 2022
Caption
Intake unit 4 is prepared for concrete pour. | November 2022
Media
Image
![Scaffolding towers and hoarding, which protects from the cold, to install trash rack guides on the intakes. | November 2022](/sites/default/files/styles/large/public/2022-12/013-STC_EV_EVVP1501_20221102-1500x.jpg?itok=NVhICxHm)
Media Name
Scaffolding towers and hoarding, which protects from the cold, to install trash rack guides on the intakes. | November 2022
Caption
Scaffolding towers and hoarding, which protects from the cold, to install trash rack guides on the intakes. | November 2022
Media
Image
![Spiral case units in the powerhouse. | November 2022](/sites/default/files/styles/large/public/2022-12/014-EVVP1590-1500x.jpg?itok=oQXm8o62)
Media Name
Spiral case units in the powerhouse. | November 2022
Caption
Spiral case units in the powerhouse. | November 2022
Media
Image
![Working on the runner, wicket gate, and stator in the pit on unit 1. | November 2022](/sites/default/files/styles/large/public/2022-12/015-EVVP1553-1500x.jpg?itok=Wor3k4EN)
Media Name
Working on the runner, wicket gate, and stator in the pit on unit 1. | November 2022
Caption
Working on the runner, wicket gate, and stator in the pit on unit 1. | November 2022
Media
Image
![Wedging the stator on unit 1 inside the powerhouse. | November 2022](/sites/default/files/styles/large/public/2022-12/016-EVVP1652-1500x.jpg?itok=eqUcpfW6)
Media Name
Wedging the stator on unit 1 inside the powerhouse. | November 2022
Caption
Wedging the stator on unit 1 inside the powerhouse. | November 2022
Media
Image
![Construction and assembly of rotors inside the powerhouse. | November 2022](/sites/default/files/styles/large/public/2022-12/017-EVVP1544-1500x_0.jpg?itok=mm136bK6)
Media Name
Construction and assembly of rotors inside the powerhouse. | November 2022
Caption
Construction and assembly of rotors inside the powerhouse. | November 2022
Media
Image
![Tilting and lifting unit 1 turbine shaft. | November 2022](/sites/default/files/styles/large/public/2022-12/01-2-1500x.jpg?itok=28XKqEBN)
Media Name
Tilting and lifting unit 1 turbine shaft. | November 2022
Caption
Tilting and lifting unit 1 turbine shaft. | November 2022
Media
Image
![Lowering unit 1 turbine shaft into position in the turbine runner. The shaft connects the turbine to the generator to produce continuous power. | November 2022](/sites/default/files/styles/large/public/2022-12/02-IMG_2399-1500x.jpg?itok=fku3myhe)
Media Name
Lowering unit 1 turbine shaft into position in the turbine runner. The shaft connects the turbine to the generator to produce continuous power. | November 2022
Caption
Lowering unit 1 turbine shaft into position in the turbine runner. The shaft connects the turbine to the generator to produce continuous power. | November 2022
Media
Image
![Dam buttress, approach channel, and stringing first transmission towers. | November 2022](/sites/default/files/styles/large/public/2022-12/03-STC_EV_1110_P5P6CORE_STRINGDJI_0989_20221110-1500x.jpg?itok=uXipz0w7)
Media Name
Dam buttress, approach channel, and stringing first transmission towers. | November 2022
Caption
Dam buttress, approach channel, and stringing first transmission towers. | November 2022
Media
Image
![There will be 11 transmission towers on site to connect the Site C dam to the Site C substation. | November 2022](/sites/default/files/styles/large/public/2022-12/04-STC_EV_1110_P5P6CORE_STRINGDJI_0991_20221110-1500x.jpg?itok=c9i2XzBZ)
Media Name
There will be 11 transmission towers on site to connect the Site C dam to the Site C substation. | November 2022
Caption
There will be 11 transmission towers on site to connect the Site C dam to the Site C substation. | November 2022
Media
Image
![Northeast-facing over the approach channel, dam buttress and dam. | November 2022](/sites/default/files/styles/large/public/2022-12/05-STC_EV_1110_P5P6CORE_STRINGDJI_0968-Pano_20221110-1500x.jpg?itok=T8t-z1x1)
Media Name
Northeast-facing over the approach channel, dam buttress and dam. | November 2022
Caption
Northeast-facing over the approach channel, dam buttress and dam. | November 2022
Media
Image
![East-facing view of the approach channel. | November 2022](/sites/default/files/styles/large/public/2022-12/06-STC_EV_1110_P5P6CORE_STRINGDJI_0967_20221110-1500x.jpg?itok=H6z_Z2TS)
Media Name
East-facing view of the approach channel. | November 2022
Caption
East-facing view of the approach channel. | November 2022
Media
Image
![Completed Cache Creek Bridge on Highway 29. | November 2022](/sites/default/files/styles/large/public/2022-12/07-STC_EV_1110_HWY29_DJI_0108_20221110-1500x.jpg?itok=mUBWN1iv)
Media Name
Completed Cache Creek Bridge on Highway 29. | November 2022
Caption
Completed Cache Creek Bridge on Highway 29. | November 2022
Media
Image
![The future Halfway River boat launch at the east side of the Halfway River Bridge. | November 2022](/sites/default/files/styles/large/public/2022-12/01-STC_EV_1110_HWY29_DJI_0070_20221110-1500x.jpg?itok=rM8ACxHp)
Media Name
The future Halfway River boat launch at the east side of the Halfway River Bridge. | November 2022
Caption
The future Halfway River boat launch at the east side of the Halfway River Bridge. | November 2022
Media
Image
![An upstream view with the approach channel at left, the powerhouse and generating station at centre, and the earthfill dam at centre. | November 2022](/sites/default/files/styles/large/public/2022-12/02-STC_EV_1116_ApproachPanoDJI_0014-Pano_20221116-1500x.jpg?itok=v18UVtAr)
Media Name
An upstream view with the approach channel at left, the powerhouse and generating station at centre, and the earthfill dam at centre. | November 2022
Caption
An upstream view with the approach channel at left, the powerhouse and generating station at centre, and the earthfill dam at centre. | November 2022
Media
Image
![Panorama of the completed Lynx Creek Bridge along Highway 29. | November 2022](/sites/default/files/styles/large/public/2022-12/04-STC_EV_DJI_0118-Pano_20221117-1500x.jpg?itok=nl3rK9ua)
Media Name
Panorama of the completed Lynx Creek Bridge along Highway 29. | November 2022
Caption
Panorama of the completed Lynx Creek Bridge along Highway 29. | November 2022
Media
Image
![New Lynx Creek highway realignment, with the existing Highway 29 at right. | November 2022](/sites/default/files/styles/large/public/2022-12/03-STC_EV_DJI_0113_20221117-1500x.jpg?itok=y-vNSblt)
Media Name
New Lynx Creek highway realignment, with the existing Highway 29 at right. | November 2022
Caption
New Lynx Creek highway realignment, with the existing Highway 29 at right. | November 2022
Media
Image
![Upstream view of the damsite. | November 2022](/sites/default/files/styles/large/public/2022-12/01-STC_1130_Appr_P6_CORE_HOWEDJI_0313_20221130-1500x.jpg?itok=hL4vNUdn)
Media Name
Upstream view of the damsite. | November 2022
Caption
Upstream view of the damsite. | November 2022
Media
Image
![From left to right: Spillways, penstocks, powerhouse and operations building, with the tailrace galleries in front. | November 2022](/sites/default/files/styles/large/public/2022-12/02-STC_1130_Appr_P6_CORE_HOWEDJI_0286-Pano_20221130-1500x.jpg?itok=DCM5OC7a)
Media Name
From left to right: Spillways, penstocks, powerhouse and operations building, with the tailrace galleries in front. | November 2022
Caption
From left to right: Spillways, penstocks, powerhouse and operations building, with the tailrace galleries in front. | November 2022
Media
Image
![From left to right: Spillways and stilling basin weirs, penstocks, powerhouse and operations building. | November 2022](/sites/default/files/styles/large/public/2022-12/03-STC_1130_Appr_P6_CORE_HOWEDJI_0260_20221130-1500x.jpg?itok=9zAdkyl1)
Media Name
From left to right: Spillways and stilling basin weirs, penstocks, powerhouse and operations building. | November 2022
Caption
From left to right: Spillways and stilling basin weirs, penstocks, powerhouse and operations building. | November 2022
Media
Image
![Permanent upstream fish passage, which helps fish migrate upstream of the dam site. | November 2022](/sites/default/files/styles/large/public/2022-12/04-STC_1130_Appr_P6_CORE_HOWEDJI_0223_20221130-1500x.jpg?itok=bn_t9zP_)
Media Name
Permanent upstream fish passage, which helps fish migrate upstream of the dam site. | November 2022
Caption
Permanent upstream fish passage, which helps fish migrate upstream of the dam site. | November 2022
Media
Image
![A gantry crane on top of intake unit 1. | November 2022](/sites/default/files/styles/large/public/2022-12/05-STC_1130_Appr_P6_CORE_HOWEDJI_0291_20221130-1500x.jpg?itok=BpsvJzh-)
Media Name
A gantry crane on top of intake unit 1. | November 2022
Caption
A gantry crane on top of intake unit 1. | November 2022
Media
Image
![The six penstocks bring water from the reservoir to the powerhouse. | November 2022](/sites/default/files/styles/large/public/2022-12/06-STC_1130_Appr_P6_CORE_HOWEDJI_0262_20221130-1500x.jpg?itok=CeVQZl9F)
Media Name
The six penstocks bring water from the reservoir to the powerhouse. | November 2022
Caption
The six penstocks bring water from the reservoir to the powerhouse. | November 2022
Media
Image
![North-facing view of the dam and buttress. | November 2022](/sites/default/files/styles/large/public/2022-12/07-STC_1130_Appr_P6_CORE_HOWEDJI_0271-Pano_20221130-1500x.jpg?itok=-wh-oXS2)
Media Name
North-facing view of the dam and buttress. | November 2022
Caption
North-facing view of the dam and buttress. | November 2022
Media
Image
![South-facing panorama of the dam. | November 2022](/sites/default/files/styles/large/public/2022-12/08-STC_1130_Appr_P6_CORE_HOWEDJI_0319-Pano_20221130-1500x.jpg?itok=OJeGUG7L)
Media Name
South-facing panorama of the dam. | November 2022
Caption
South-facing panorama of the dam. | November 2022
Media
Image
![The dam buttress, with the earthfill dam under construction. Its height is currently 445 metres above sea level. | November 2022](/sites/default/files/styles/large/public/2022-12/09-STC_1130_Appr_P6_CORE_HOWEDJI_0263_20221130-1500x.jpg?itok=8I_fJctq)
Media Name
The dam buttress, with the earthfill dam under construction. Its height is currently 445 metres above sea level. | November 2022
Caption
The dam buttress, with the earthfill dam under construction. Its height is currently 445 metres above sea level. | November 2022
Media
Image
![The inlet portals (left) where the Peace River enters the diversion tunnels, and the earthfill dam (centre) being built. | November 2022](/sites/default/files/styles/large/public/2022-12/010-STC_1130_Appr_P6_CORE_HOWEDJI_0332-Pano_20221130-1500x.jpg?itok=Mc0XwFII)
Media Name
The inlet portals (left) where the Peace River enters the diversion tunnels, and the earthfill dam (centre) being built. | November 2022
Caption
The inlet portals (left) where the Peace River enters the diversion tunnels, and the earthfill dam (centre) being built. | November 2022
Order
1.00