Plinth construction underway on the approach channel |June 2022
Media
Image
Media Name
Construction of the spillways, the upper headworks and the stilling basin weirs, which is used for slowing the energy of the water. | June 2022
Media
Image
Media Name
Upstream view of the spillway upper headworks. |June 2022
Media
Image
Media Name
Intake units 1, 2, 3 and 6 are at full elevation and construction on intake units 4 and 5 continues. | June 2022
Media
Image
Media Name
Penstock unit 4 nears completion. | June 2022
Media
Image
Media Name
Penstock units 4 and 5 are connected to the powerhouse. | June 2022
Media
Image
Media Name
Units 6 to 1 inside the powerhouse are in varying stages of construction. | June 2022
Media
Image
Media Name
Cache Creek Bridge concrete pouring. | June 2022
Media
Image
Media Name
Paving the east approach of the Halfway River Bridge on Highway 29. | June 2022
Media
Image
Media Name
Paving the west approach of the Halfway River Bridge on Highway 29. | June 2022
Media
Image
Media Name
Farrell Creek placement of pre-cast concrete panels | June 2022
Media
Image
Media Name
Constructing the embankment at the east end of the Lynx Creek Rd. realignment on Highway 29. | June 2022
Media
Image
Media Name
Preparing to pour concrete on the Lynx Creek Bridge. | June 2022
Media
Image
Media Name
The second to last penstock segment waits for installation on penstock unit 4. | June 2022
Media
Image
Media Name
Spiral case units 6 to 1 in varying stages of construction inside the powerhouse. Spiral case units 4 and 3 are ready to be encased in concrete. | June 2022
Media
Image
Media Name
Unit 6 spiral case fabrication is ongoing. | June 2022
Media
Image
Media Name
Unit 5 spiral case and upper pit liner. | June 2022
Media
Image
Media Name
Top view of unit 4 spiral case and upper pit liner. | June 2022
Media
Image
Media Name
Unit 4 spiral case and upper pit liner is installed with piping. | June 2022
Media
Image
Media Name
Unit 1 and 2 rotor fabrication. | June 2022
Media
Image
Media Name
Unit 1 rotor. | June 2022
Media
Image
Media Name
Installation of cable trays is underway in the powerhouse. | June 2022
Media
Image
Media Name
Balance of plant infrastructure installations continue. | June 2022
Media
Image
Media Name
Unit 1 coupling chamber – the closure section is on the and the penstock is on the right. | June 2022
Media
Image
Media Name
Cache Creek Bridge third concrete pour underway. | June 2022
Media
Image
Media Name
First concrete pour on the Lynx Creek Bridge deck. | June 2022
Media
Image
Media Name
In-river construction of a spawning shoal near the Peace Canyon Dam on the Peace River. | June 2022
Media
Image
Media Name
This is the final segment of the last penstock unit. The six penstock units needed for the powerhouse are made up of 90 segments. | June 2022
Media
Image
Media Name
The last penstock segment is lifted the and turned into position for the correct installation angle into the powerhouse. | June 2022
Media
Image
Media Name
Moving the final segment over penstock unit 3 to its position on penstock unit 4. | June 2022
Media
Image
Media Name
The last penstock segment is lowered into position. | June 2022
Media
Image
Media Name
Welding penstock segments together. | June 2022
Media
Image
Media Name
Large bolts connect the two penstock segments together. | June 2022
Media
Image
Media Name
Work to build a spawning shoal near Maurice Creek is ongoing. | June 2022
Media
Image
Media Name
Lynx Creek Bridge before the for the final concrete pour. | June 2022
Media
Image
Media Name
Dry Creek Bridge final slope treatment below the bridge and work on the east approach continues. | June 2022
Media
Image
Media Name
Concrete is poured on Farrell Creek Bridge for the abutment, while the crews complete deck panels and formwork on the west end of the bridge. | June 2022
Media
Image
Media Name
Safety railings are installed at Halfway River Bridge. | June 2022
Media
Image
Media Name
Three of seven concrete pours complete on Cache Creek Bridge. | June 2022
Media
Image
Media Name
The largest of several ponds totalling 50 hectares at the Golata Creek wetland. | June 2022
Media
Image
Media Name
85th Avenue industrial lands where glacial till is extracted and brought to Site C to build the dam. | June 22