Media
Image
Media Name
Spillways, penstocks, powerhouse and operations building. | May 2022
Media
Image
Media Name
From left penstock units 6 through to unit 1 in varying stages of construction. | May 2022
Media
Image
Media Name
North facing view of the spillways. | May 2022
Media
Image
Media Name
East facing view of the approach channel under construction. | May 2022
Media
Image
Media Name
A pre-cast concrete panel is lifted into place between piers two and three on the Farrell Creek bridge. | May 2022
Media
Image
Media Name
Pre-cast concrete panels have been placed between piers two and three on the Highway 29 bridge realignment at Farrell Creek. | May 2022
Media
Image
Media Name
Lifting a pre-cast deck panel into place on the Highway 29 Farrell Creek bridge realignment. | May 2022
Media
Image
Media Name
Pre-cast concrete panels are moved into position on the Farrell Creek bridge at the Highway 29 realignment. | May 2022
Media
Image
Media Name
An upstream view of the powerhouse and generating station, with laydown areas, temporary fishway and outlet portals. | May 2022
Media
Image
Media Name
Ongoing construction of the approach channel. | May 2022
Media
Image
Media
Image
Media Name
These large concrete blocks are the stilling basin weirs used to take the energy out of the falling water. | May 2022
Media
Image
Media Name
The powerhouse and operation building are substantially complete, with foundation enhancement work ongoing in front of the tailrace. | May 2022
Media
Image
Media Name
Six penstock units are in various stages of completion. | May 2022
Order
8.00