Our latest employment statistics show there were 4,175 total workers on the Site C project in December 2021. Of the total workers, 2,977 were from British Columbia, or 71 per cent. There were 840 workers on site from the Peace River Regional District – that's 24 per cent of the construction and non-construction contractor’s workforce.
Site C employment statistics - December 2021
https://sitecproject.comhttps://www.sitecproject.com/news-and-information/monthly-employment-statistics
Latest Information
BC Hydro achieves penultimate milestone with fifth generating unit online at Site C
The Site C project has reached one of its last major milestones with the successful commissioning of the fifth generating unit.
BC Hydro’s Site C GO Fund Reaches $1 Million Milestone, Final Grants Awarded
BC Hydro is awarding $80,000 to nine non-profit organizations in the Peace region through the final intake of the Site C project's GO Fund, concluding the program as the project nears completion later this year.
Site C reaches new milestone with fourth generating unit online
Two-thirds of the project’s generating capacity is now operational, significantly bolstering British Columbia’s energy supply.