![Removing material from between the downstream and upstream cofferdams. Both cofferdams completely seal off the Peace River so that work on the earthfill dam can begin. | February 2021](/sites/default/files/styles/large/public/2022-02/01-EVVP18271220210211-1500x.jpg?itok=0nfAXrTZ)
Media Name
Removing material from between the downstream and upstream cofferdams. Both cofferdams completely seal off the Peace River so that work on the earthfill dam can begin. | February 2021
Caption
Removing material from between the downstream and upstream cofferdams. Both cofferdams completely seal off the Peace River so that work on the earthfill dam can begin. | February 2021
Media
Image
![Delivery and storage area for rip-rap used at the upstream cofferdam. The upstream cofferdam has been completed. | February 2021](/sites/default/files/styles/large/public/2022-02/02-EVVP18331220210211-1500x.jpg?itok=dTr6XIeJ)
Media Name
Delivery and storage area for rip-rap used at the upstream cofferdam. The upstream cofferdam has been completed. | February 2021
Caption
Delivery and storage area for rip-rap used at the upstream cofferdam. The upstream cofferdam has been completed. | February 2021
Media
Image
![Intake units 1 and unit 3 are nearing completion as part of the ongoing powerhouse construction. This includes concrete placements at the powerhouse, intakes and spillway, installation of penstock segments, and construction of the steel super-structure for the powerhouse. | February 2021](/sites/default/files/styles/large/public/2022-02/03-EVVP18201120210211-1500x.jpg?itok=0nlFenGq)
Media Name
Intake units 1 and unit 3 are nearing completion as part of the ongoing powerhouse construction. This includes concrete placements at the powerhouse, intakes and spillway, installation of penstock segments, and construction of the steel super-structure fo
Caption
Intake units 1 and unit 3 are nearing completion as part of the ongoing powerhouse construction. This includes concrete placements at the powerhouse, intakes and spillway, installation of penstock segments, and construction of the steel super-structure for the powerhouse. | February 2021
Media
Image
![Aerial view of five of six penstocks under construction. A penstock is a large steel pipe in a hydroelectric generating station that brings water from the reservoir to a turbine. | February 2021](/sites/default/files/styles/large/public/2022-02/02-DJI_00421120210216-1500x_1.jpg?itok=l_qJy-3q)
Media Name
Aerial view of five of six penstocks under construction. A penstock is a large steel pipe in a hydroelectric generating station that brings water from the reservoir to a turbine. | February 2021
Caption
Aerial view of five of six penstocks under construction. A penstock is a large steel pipe in a hydroelectric generating station that brings water from the reservoir to a turbine. | February 2021
Media
Image
![Crews pour concrete at the lower level spillway gates. The dam spillways will allow the passage of large volumes of water from the reservoir into the river channel downstream. | February 2021](/sites/default/files/styles/large/public/2022-02/03-EVVP18361220210216-1500x_1.jpg?itok=SMhRFw3U)
Media Name
Crews pour concrete at the lower level spillway gates. The dam spillways will allow the passage of large volumes of water from the reservoir into the river channel downstream. | February 2021
Caption
Crews pour concrete at the lower level spillway gates. The dam spillways will allow the passage of large volumes of water from the reservoir into the river channel downstream. | February 2021
Media
Image
![Aerial view of the Halfway River bridge. | February 2021](/sites/default/files/styles/large/public/2022-02/04-DJI_0073-Pano1320210217-1500x_2.jpg?itok=eivVQi6e)
Media Name
Aerial view of the Halfway River bridge. | February 2021
Caption
Aerial view of the Halfway River bridge. | February 2021
Media
Image
![Crews at the Halfway River bridge use a survey buggy to measure the angle of the bridge girders before installing the bridge deck. All twelve bridge piers are complete and steel girders are being installed on top. | February 2021](/sites/default/files/styles/large/public/2022-02/05-DJI_00541320210217-1500x_1.jpg?itok=wrDEHo4j)
Media Name
Crews at the Halfway River bridge use a survey buggy to measure the angle of the bridge girders before installing the bridge deck. All twelve bridge piers are complete and steel girders are being installed on top. | February 2021
Caption
Crews at the Halfway River bridge use a survey buggy to measure the angle of the bridge girders before installing the bridge deck. All twelve bridge piers are complete and steel girders are being installed on top. | February 2021
Media
Image
![Halfway River bridge girder installation is underway. When complete, the new bridge will be one kilometre long. | February 2021](/sites/default/files/styles/large/public/2022-02/06-DJI_00591320210217-1500x_1.jpg?itok=sN1hTiyX)
Media Name
Halfway River bridge girder installation is underway. When complete, the new bridge will be one kilometre long. | February 2021
Caption
Halfway River bridge girder installation is underway. When complete, the new bridge will be one kilometre long. | February 2021
Media
Image
![Crews drill piles for pier 1 of the Farrell Creek bridge. Construction is underway on the new highway segment and bridge at Farrell Creek. | February 2021](/sites/default/files/styles/large/public/2022-02/07-DJI_00341220210217-1500x_1.jpg?itok=_HQjIM73)
Media Name
Crews drill piles for pier 1 of the Farrell Creek bridge. Construction is underway on the new highway segment and bridge at Farrell Creek. | February 2021
Caption
Crews drill piles for pier 1 of the Farrell Creek bridge. Construction is underway on the new highway segment and bridge at Farrell Creek. | February 2021
Media
Image
![The Cache Creek temporary construction bridge at the Highway 29 realignment is in place. Bridge approaches will be completed in spring 2021. |February 2021](/sites/default/files/styles/large/public/2022-02/01-DJI_00491120210223-1500x_0.jpg?itok=akzFDMZL)
Media Name
The Cache Creek temporary construction bridge at the Highway 29 realignment is in place. Bridge approaches will be completed in spring 2021. |February 2021
Caption
The Cache Creek temporary construction bridge at the Highway 29 realignment is in place. Bridge approaches will be completed in spring 2021. |February 2021
Media
Image
![An aerial view of the Highway 29 realignment section at Cache Creek. |February 2021](/sites/default/files/styles/large/public/2022-02/02-DJI_00151120210223-1500x_0.jpg?itok=4NDDJ9YM)
Media Name
An aerial view of the Highway 29 realignment section at Cache Creek. |February 2021
Caption
An aerial view of the Highway 29 realignment section at Cache Creek. |February 2021
Media
Image
![A panoramic view of the Lynx Creek segment of the Highway 29 realignment where construction is underway. |February 2021](/sites/default/files/styles/large/public/2022-02/04-DJI_0101-Pano1220210223-1500x_0.jpg?itok=niFcD3fz)
Media Name
A panoramic view of the Lynx Creek segment of the Highway 29 realignment where construction is underway. |February 2021
Caption
A panoramic view of the Lynx Creek segment of the Highway 29 realignment where construction is underway. |February 2021
Media
Image
![Construction continues on shoreline protection work in Hudson’s Hope. |February 2021](/sites/default/files/styles/large/public/2022-02/05-DJI_01101320210223-1500x_0.jpg?itok=rcIqVA_K)
Media Name
Construction continues on shoreline protection work in Hudson’s Hope. |February 2021
Caption
Construction continues on shoreline protection work in Hudson’s Hope. |February 2021
Media
Image
![Crews have commenced installation of the turbine-embedded components for Units 1 and 2 inside the powerhouse. The Unit 1 draft tube cone and thrust ring are being prepared for stay ring installation. | February 2021](/sites/default/files/styles/large/public/2022-02/01-EVVP20801420210224-1500x_2.jpg?itok=LhQ5z_yb)
Media Name
Crews have commenced installation of the turbine-embedded components for Units 1 and 2 inside the powerhouse. The Unit 1 draft tube cone and thrust ring are being prepared for stay ring installation. | February 2021
Caption
Crews have commenced installation of the turbine-embedded components for Units 1 and 2 inside the powerhouse. The Unit 1 draft tube cone and thrust ring are being prepared for stay ring installation. | February 2021
Media
Image
![The Unit 1 stay ring is lowered into place using a crane. | February 2021](/sites/default/files/styles/large/public/2022-02/02-20210225-Stay-ring-craned-into-Unit1-1500x_2.jpg?itok=PUQuokmI)
Media Name
The Unit 1 stay ring is lowered into place using a crane. | February 2021
Caption
The Unit 1 stay ring is lowered into place using a crane. | February 2021
Media
Image
![Crews install a crane rail in the powerhouse. | February 2021](/sites/default/files/styles/large/public/2022-02/04-EVVP19811320210224-1500x_2.jpg?itok=-xInE9rY)
Media Name
Crews install a crane rail in the powerhouse. | February 2021
Caption
Crews install a crane rail in the powerhouse. | February 2021
Media
Image
![The Unit 2 penstock is being prepared for installation of the flexible coupling. | February 2021](/sites/default/files/styles/large/public/2022-02/06-EVVP20211420210224-1500x_2.jpg?itok=6q6vlVzK)
Media Name
The Unit 2 penstock is being prepared for installation of the flexible coupling. | February 2021
Caption
The Unit 2 penstock is being prepared for installation of the flexible coupling. | February 2021
Media
Image
![Powerhouse steel superstructure construction. The powerhouse construction also includes concrete placements at the powerhouse, intakes and spillway, installation of penstock segments. | February 2021](/sites/default/files/styles/large/public/2022-02/07-EVVP19721320210224-1500x_2.jpg?itok=rqHMMdGA)
Media Name
Powerhouse steel superstructure construction. The powerhouse construction also includes concrete placements at the powerhouse, intakes and spillway, installation of penstock segments. | February 2021
Caption
Powerhouse steel superstructure construction. The powerhouse construction also includes concrete placements at the powerhouse, intakes and spillway, installation of penstock segments. | February 2021
Media
Image
![A view from a spillway of a coupling chamber opening for Units 3 and 4. | February 2021](/sites/default/files/styles/large/public/2022-02/08-EVVP21081420210224-1500x.jpg?itok=MnCQlp9Z)
Media Name
A view from a spillway of a coupling chamber opening for Units 3 and 4. | February 2021
Caption
A view from a spillway of a coupling chamber opening for Units 3 and 4. | February 2021
Order