A concrete placement takes place at the intake area of the powerhouse. So far, approximately 117,400 m3 of a total of 683,000 m3 of conventional concrete has been placed at the generating station and spillways. | January 2020
Media
Image
Media Name
Penstock construction of units 1, 2 and 3 progresses. | January 2020