Crews place roller-compacted concrete on the dam and core buttress. | May 2021
Media
Image
Media Name
Installation of reinforcing steel on the south face of the roller-compacted concrete dam and core surface. | May 2021
Media
Image
Media Name
A worker sprays mist on the roller-compacted concrete surface before the next layer of concrete is placed. | May 2021
Media
Image
Media Name
South-facing view of the dam core trench. The white tarps are covering stockpiled dam core till materials. | May 2021
Media
Image
Media Name
Dismantling the access assembly platforms on a newly erected tower crane at the spillway basin. | May 2021
Media
Image
Media Name
Dismantling the access assembly platforms on a newly erected tower crane at the spillway basin. | May 2021
Media
Image
Media Name
Construction on the Highway 29 realignment at Cache Creek. Crews are working on grading, drainage and bridge foundation works. | May 2021
Media
Image
Media Name
Construction continues on the new Highway 29 realignment and bridge foundation works at Farrell Creek. | May 2021
Media
Image
Media Name
Construction on the new Highway 29 realignment at Farrell Creek. Crews are installing rebar, formwork and pouring concrete as part of the bridge foundation works. | May 2021
Media
Image
Media Name
Work continues on the new Lynx Creek embankment on Highway 29, where crews are excavating and hauling rock aggregates to construct the highway. | May 2021
Media
Image
Media Name
Construction is underway on the 1.5-kilometre-long section of Highway 29 at Dry Creek. Crews are also installing rock anchors and constructing concrete bridge foundations on the new 158-metre-long bridge. | May 2021
Media
Image
Media Name
The construction of a 2.6-kilometre-long berm to protect the shoreline of Hudson's Hope is underway. Crews are clearing vegetation and placing material along the shoreline to build the berm. | May 2021
Media
Image
Media Name
Six bridge piers in various stages of construction at Cache Creek. The new reservoir will cover the existing Highway 29 at Cache Creek East, requiring the construction of a new highway segment and a new bridge. | May 2021
Media
Image
Media Name
Halfway River bridge showing cast-in-place bridge deck construction. The new bridge is one kilometre long. | May 2021
Media
Image
Media Name
Upper Gates Island material extraction area for building the Lynx Creek embankment on Highway 29. The Lynx Creek segment is eight kilometres long and is the longest segment of highway to be realigned. | May 2021
Media
Image
Media Name
The first of two columns is complete on the new 158-metre-long bridge on Highway 29 at Dry Creek. | May 2021
Media
Image
Media Name
The Portage Mountain Quarry is a source of rock materials used for various segments of the Highway 29 realignment construction. Also pictured are the haul road and stockpile area. | May 2021
Media
Image
Media Name
Constructing the approach channel at Site C requires moving seven million cubic metres of soil and rock. | May 2021
Media
Image
Media Name
Roller-compacted concrete placement continues at the dam and core buttress on the south bank. | May 2021
Media
Image
Media Name
The generating station will have six penstocks to direct water into its six turbine and generator units. The Unit 1 penstock is almost complete with crews currently working on the concrete casing. | May 2021
Media
Image
Media Name
An aerial view of installation underway on the Unit 5 intake transition penstock section. | May 2021
Media
Image
Media Name
Upper spillway headworks under construction. The spillway will allow the passage of large volumes of water from the reservoir into the river channel downstream. | May 2021
Media
Image
Media Name
Spillway headworks work at the west low-level outlet. | May 2021
Media
Image
Media Name
A bridge crane girder section is lowered into position at the auxiliary service bay of the powerhouse. | May 2021
Media
Image
Media Name
Powerhouse component installation is underway for Units 1, 2, and 3. | May 2021
Media
Image
Media Name
Unit 1 spiral case installation. The spiral case regulates water flow and pressure into the turbine. | May 2021