Media
Image
Media Name
An aerial view of the headpond and debris boom where a spud barge is used for clearing debris materials from the boom. | July 2021
Media
Image
Media Name
Construction progresses at the spillway headworks east low-level outlet gate. The spillway will allow the passage of large volumes of water from the reservoir into the river channel downstream. | July 2021
Media
Image
Media Name
Installing scaffolding at the spillway headworks low-level outlet. | July 2021
Media
Image
Media Name
Spillway headworks low-level outlet gate and low-level maintenance gate. | July 2021
Media
Image
Media Name
East-facing view of five of six penstock units in varying stages of construction. | July 2021
Media
Image
Media Name
Penstock units 1, 2, and 3, with the intake gates. | July 2021
Media
Image
Media Name
Spiral case units 1, 2, and 3, are under construction in the powerhouse. | July 2021
Media
Image
Media Name
The new detour at Lynx Creek east on Highway 29 is now open to vehicle traffic. | July 2021
Media
Image
Media Name
West-facing view of the east-end of the Lynx Creek alignment on Highway 29 showing the recently paved detour. | July 2021
Media
Image
Media Name
East-facing view of the paved detour at the Lynx Creek east alignment on Highway 29. | July 2021
Media
Image
Media Name
The east section of the Lynx Creek Highway 29 alignment is under construction to the north of the existing highway. | July 2021
Media
Image
Media Name
Clearing and grubbing is completed for the Lynx Creek alignment on Highway 29. | July 2021
Media
Image
Media Name
Bridge formwork is under construction at the Dry Creek section of Highway 29. | July 2021
Media
Image
Media Name
Highway 29 alignment at Cache Creek in varying stages of construction, showing the abutments at both ends of six bridge piers. | July 2021
Media
Image
Media Name
Highway 29 alignment at Farrell Creek in varying stages of construction, showing the abutments at either end with five bridge piers. | July 2021
Media
Image
Media Name
Workers install rebar for the east abutment of the Farrell Creek bridge on Highway 29. | July 2021
Media
Image
Media Name
The west abutment of the Farrell Creek bridge alignment on Highway 29. | July 2021
Media
Image
Media Name
The Dry Creek alignment on Highway 29 shows work at the east abutment and the formwork installation for a bridge pier cap. | July 2021
Media
Image
Media Name
The Lynx Creek bridge alignment on Highway 29 showing the east abutment, bridge pier 2 formwork, pier 1 wrapped in plastic for concrete curing, and the west abutment under construction. | July 2021
Media
Image
Media Name
The east portion of the Hudson’s Hope shoreline protection is being built. | July 2021
Media
Image
Media Name
The glacial till to build the Site C dam is sorted at the 85th Avenue industrial land. Sorting is arranged based on where till will be placed in the dam core. | July 2021
Media
Image
Media Name
The 85th Avenue conveyor and till feeder operations are shown at centre. | July 2021
Media
Image
Media Name
Crews prepare the left bank and remove of a top shale bedrock layer, to prepare for glacial till placement. | July 2021
Media
Image
Media Name
White tarpaulins are placed over freshly laid glacial till in the dam core trench to maintain moisture content. | July 2021
Media
Image
Media Name
Aggregate material is filtered and placed in the dam’s downstream shell. At centre, the top layer is removed to access the bedrock layer in the core trench. | July 2021
Media
Image
Media Name
The first of four spiral case inlet bulkheads is delivered from the Voith warehouse at site to the powerhouse. | July 2021
Media
Image
Media Name
The bulkhead has a 10-metre interior diameter and weighs 27 tonnes. | July 2021
Media
Image
Media Name
The bulkhead is lowered into the coupling chamber where it is positioned against the upstream end of the spiral case. | July 2021
Media
Image
Media Name
The spiral case bulkhead is welded in place to complete the hydrostatic test and pressurized seal of the spiral case. | July 2021
Media
Image
Media Name
Construction is ongoing on the Roller-Compacted Concrete (RCC) Buttress and the dam core trench. | July 2021
Media
Image
Media Name
Spillway and powerhouse construction are ongoing with the Roller-Compacted Concrete (RCC) Buttress and the approach channel in the background. | July 2021
Media
Image
Media Name
Approach channel excavation continues with rip-rap placement ongoing along the length of the upper edge of the south bank. | July 2021
Media
Image
Media Name
A top view (from right to left) of the unit 1 to 6 intakes and penstocks in varying stages of construction. Unit 4 is going to be the last to be built. | July 2021
Media
Image
Media Name
The west low-level outlet piers at the spillway are under construction. | July 2021
Media
Image
Media Name
Concrete placement at the auxiliary spillway overflow channel. | July 2021
Media
Image
Media Name
Concrete placement at the auxiliary spillway overflow channel. | July 2021
Media
Image
Media Name
First stage concrete is complete for the unit 6 draft tube inside the powerhouse. | July 2021
Media
Image
Media Name
Installation of the unit 5 draft tube elbow is in progress. | July 2021
Media
Image
Media Name
Second stage concrete curing is underway around the unit 4 draft tube cone. | July 2021
Media
Image
Media Name
The unit 3 thrust ring and stay ring have been installed. Crews are building the temporary supports for the spiral case installation. | July 2021
Media
Image
Media Name
The spiral case installation for unit 2 is underway. Robotic and semi-automatic complete joint penetration welding is in progress. | July 2021
Media
Image
Media Name
Crews are removing the temporary welding platforms for unit 1 in preparation for a range of inspection processes. | July 2021