Media
Image

Media Name
A pier is tarped to protect the transition cone on the Cache Creek bridge. | November 2021
Caption
A pier is tarped to protect the transition cone on the Cache Creek bridge. | November 2021
Media
Image

Media Name
Steel girder installation is complete on the Lynx Creek bridge. | November 2021
Caption
Steel girder installation is complete on the Lynx Creek bridge. | November 2021
Media
Image

Media Name
A lift of rebar is lowered at intake unit 6. | November 2021
Caption
A lift of rebar is lowered at intake unit 6. | November 2021
Media
Image

Media Name
A lift of rebar is received and unhooked from the crane. | November 2021
Caption
A lift of rebar is received and unhooked from the crane. | November 2021
Media
Image

Media Name
An overview of the dam core, where work continues on the upstream dam shell. | November 2021
Caption
An overview of the dam core, where work continues on the upstream dam shell. | November 2021
Media
Image

Media Name
Approximately three metres of fill material is spread over the compacted glacial till layer to stop frost from penetrating through. | November 2021
Caption
Approximately three metres of fill material is spread over the compacted glacial till layer to stop frost from penetrating through. | November 2021
Media
Image

Media Name
Dismantling the temporary access ramp to the dam and core buttress that was used for roller-compacted concrete placement. | November 2021
Caption
Dismantling the temporary access ramp to the dam and core buttress that was used for roller-compacted concrete placement. | November 2021
Media
Image

Media Name
Panorama of the Site C construction site, looking downstream. | November 2021
Caption
Panorama of the Site C construction site, looking downstream. | November 2021
Media
Image

Media Name
The Peace River debris collection boom and barge have been removed from the river for the winter. Both will be reinstalled in the spring. | November 2021
Caption
The Peace River debris collection boom and barge have been removed from the river for the winter. Both will be reinstalled in the spring. | November 2021
Media
Image

Media Name
A temporary ramp allows equipment to reach the higher areas of the left bank core trench abutment to complete the grouting curtain. | November 2021
Caption
A temporary ramp allows equipment to reach the higher areas of the left bank core trench abutment to complete the grouting curtain. | November 2021
Media
Image

Media Name
A side view of the temporary access ramp at the left core trench abutment that allows equipment to grout the higher elevations of the abutment. | November 2021
Caption
A side view of the temporary access ramp at the left core trench abutment that allows equipment to grout the higher elevations of the abutment. | November 2021
Media
Image

Media Name
The remaining four (of six) Site C turbine runners arrived from São Paulo, Brazil, at the Port of Prince Rupert on November 19, 2021. | November 2021
Caption
The remaining four (of six) Site C turbine runners arrived from São Paulo, Brazil, at the Port of Prince Rupert on November 19, 2021. | November 2021
Media
Image

Media Name
An upstream view of the Site C construction site. | November 2021
Caption
An upstream view of the Site C construction site. | November 2021
Media
Image

Media Name
A temporary ramp is installed higher on the left bank core trench abutment to enable completion of the grout curtain. | November 2021
Caption
A temporary ramp is installed higher on the left bank core trench abutment to enable completion of the grout curtain. | November 2021
Media
Image

Media Name
Construction of the upstream shell of the dam. | November 2021
Caption
Construction of the upstream shell of the dam. | November 2021
Media
Image

Media Name
Spiral case installation inside the powerhouse.| November 2021
Caption
Spiral case installation inside the powerhouse.| November 2021
Media
Image

Media Name
Spiral case assembly is underway on generating unit 4. | November 2021
Caption
Spiral case assembly is underway on generating unit 4. | November 2021
Media
Image

Media Name
Unit 6 draft tube cone. | November 2021
Caption
Unit 6 draft tube cone. | November 2021
Media
Image

Media Name
The Site C penstock units in varying stages of construction. | November 2021
Caption
The Site C penstock units in varying stages of construction. | November 2021
Media
Image

Media Name
Staging the external welding platform on penstock unit 4. | November 2021
Caption
Staging the external welding platform on penstock unit 4. | November 2021
Media
Image

Media Name
Northwest view of the approach channel excavation. | November 2021
Caption
Northwest view of the approach channel excavation. | November 2021
Media
Image

Media Name
Approach channel | November 2021
Caption
Approach channel | November 2021
Order
2.00