Media
Image
![Crane mats, used to distribute weight, are placed above penstock unit 2. | August 2021](/sites/default/files/styles/large/public/2022-02/04-STC_EV_EVVP8920-Pano-20210803.jpg?itok=ckaX_Gd8)
Media Name
Crane mats, used to distribute weight, are placed above penstock unit 2. | August 2021
Caption
Crane mats, used to distribute weight, are placed above penstock unit 2. | August 2021
Media
Image
![Intake units 1 and 3 are substantially complete, with unit 2 under construction. The unit 4 penstock transition piece is pictured in the foreground. | August 2021](/sites/default/files/styles/large/public/2022-02/06-STC_EV_EVVP8757-20210803.jpg?itok=2l_WHxe3)
Media Name
Intake units 1 and 3 are substantially complete, with unit 2 under construction. The unit 4 penstock transition piece is pictured in the foreground. | August 2021
Caption
Intake units 1 and 3 are substantially complete, with unit 2 under construction. The unit 4 penstock transition piece is pictured in the foreground. | August 2021
Media
Image
![Intake unit 5 is under construction. | August 2021](/sites/default/files/styles/large/public/2022-02/07-STC_EV_EVVP8782-20210803.jpg?itok=VDb7c47f)
Media
Image
![Backfilling with granular material is ongoing in the powerhouse yard where the elevation will be at the same level as the powerhouse floor. | August 2021](/sites/default/files/styles/large/public/2022-02/08-STC_EV_EVVP8794-20210803.jpg?itok=ASHUrwrx)
Media Name
Backfilling with granular material is ongoing in the powerhouse yard where the elevation will be at the same level as the powerhouse floor. | August 2021
Caption
Backfilling with granular material is ongoing in the powerhouse yard where the elevation will be at the same level as the powerhouse floor. | August 2021
Media
Image
![Construction is ongoing on the spillway headworks centre pier at bay 2 and 3. | August 2021](/sites/default/files/styles/large/public/2022-02/09-STC_EV_EVVP8878-20210803.jpg?itok=-HJ0RU6t)
Media Name
Construction is ongoing on the spillway headworks centre pier at bay 2 and 3. | August 2021
Caption
Construction is ongoing on the spillway headworks centre pier at bay 2 and 3. | August 2021
Media
Image
![Material is removed from the upstream side of the dam core trench. | August 2021](/sites/default/files/styles/large/public/2021-11/01-STC_EV_EVVP8960-20210804-1500x.jpg?itok=C_5qBODl)
Media Name
Material is removed from the upstream side of the dam core trench. | August 2021
Caption
Material is removed from the upstream side of the dam core trench. | August 2021
Media
Image
![There is a lot of activity happening in the dam core trench, including drying glacial till, cleaning the bedrock layer and placing filters and aggregates. | August 2021](/sites/default/files/styles/large/public/2021-11/02-STC_EV_EVVP9074-20210804-1500x.jpg?itok=_wxz-UGU)
Media Name
There is a lot of activity happening in the dam core trench, including drying glacial till, cleaning the bedrock layer and placing filters and aggregates. | August 2021
Caption
There is a lot of activity happening in the dam core trench, including drying glacial till, cleaning the bedrock layer and placing filters and aggregates. | August 2021
Media
Image
![Moving material near the dam and core roller-compacted concrete buttress. | August 2021](/sites/default/files/styles/large/public/2021-11/03-STC_EV_EVVP9072-20210804-1500x.jpg?itok=dpBCQOCd)
Media Name
Moving material near the dam and core roller-compacted concrete buttress. | August 2021
Caption
Moving material near the dam and core roller-compacted concrete buttress. | August 2021
Media
Image
![Bedrock is mapped before backfilling. | August 2021](/sites/default/files/styles/large/public/2021-11/04-STC_EV_EVVP9086-20210804-1500x.jpg?itok=vgWxNLGT)
Media Name
Bedrock is mapped before backfilling. | August 2021
Caption
Bedrock is mapped before backfilling. | August 2021
Media
Image
![Formwork installation on the eastern spillway wall. | August 2021](/sites/default/files/styles/large/public/2021-11/05-STC_EV_EVVP9037-20210804-1500x.jpg?itok=zbem1xP_)
Media Name
Formwork installation on the eastern spillway wall. | August 2021
Caption
Formwork installation on the eastern spillway wall. | August 2021
Media
Image
![Spillway headworks underway. | August 2021](/sites/default/files/styles/large/public/2021-11/06-STC_EV_EVVP9241-20210809-1500x.jpg?itok=rtTI3hl1)
Media Name
Spillway headworks underway. | August 2021
Caption
Spillway headworks underway. | August 2021
Media
Image
![Tying rebar is one of the final steps before paving of the Halfway River bridge on Highway 29. | August 2021](/sites/default/files/styles/large/public/2021-11/07-EVVP9473-1500x.jpg?itok=wc3avXZn)
Media Name
Tying rebar is one of the final steps before paving of the Halfway River bridge on Highway 29. | August 2021
Caption
Tying rebar is one of the final steps before paving of the Halfway River bridge on Highway 29. | August 2021
Media
Image
![It took 2,300 cubic metres of concrete poured in 13 segments, to complete the deck of the Halfway River bridge. | August 2021](/sites/default/files/styles/large/public/2021-11/08-STC_EV_DJI_0834-Pano-20210812-1500x.jpg?itok=qE3Dzdd0)
Media Name
It took 2,300 cubic metres of concrete poured in 13 segments, to complete the deck of the Halfway River bridge. | August 2021
Caption
It took 2,300 cubic metres of concrete poured in 13 segments, to complete the deck of the Halfway River bridge. | August 2021
Media
Image
![The concrete needed for the Halfway River bridge is made at site and transported to the bridge where it is pumped onto the bridge deck. | August 2021](/sites/default/files/styles/large/public/2021-11/09-STC_EV_DJI_0846-20210812-1500x.jpg?itok=Re3HcFhT)
Media Name
The concrete needed for the Halfway River bridge is made at site and transported to the bridge where it is pumped onto the bridge deck. | August 2021
Caption
The concrete needed for the Halfway River bridge is made at site and transported to the bridge where it is pumped onto the bridge deck. | August 2021
Media
Image
![View of the nearly complete Halfway River bridge for the Highway 29 realignment. | August 2021](/sites/default/files/styles/large/public/2021-11/10-EVVP9504-1500x.jpg?itok=Ytdf7b1P)
Media Name
View of the nearly complete Halfway River bridge for the Highway 29 realignment. | August 2021
Caption
View of the nearly complete Halfway River bridge for the Highway 29 realignment. | August 2021
Media
Image
![View of the recently completed east abutment concrete of the Farrell Creek road realignment along Highway 29. | August 2021](/sites/default/files/styles/large/public/2021-11/11-EVVP9441-Pano-1500x.jpg?itok=zICyAnwu)
Media Name
View of the recently completed east abutment concrete of the Farrell Creek road realignment along Highway 29. | August 2021
Caption
View of the recently completed east abutment concrete of the Farrell Creek road realignment along Highway 29. | August 2021
Media
Image
![Placement of the granular sub-base for the Farrell Creek road realignment along Highway 29. | August 2021](/sites/default/files/styles/large/public/2021-11/12-EVVP9438-1500x.jpg?itok=Wzuq4iIV)
Media Name
Placement of the granular sub-base for the Farrell Creek road realignment along Highway 29. | August 2021
Caption
Placement of the granular sub-base for the Farrell Creek road realignment along Highway 29. | August 2021
Media
Image
![Structural steel is installed for the Highway 29 Dry Creek bridge realignment. | August 2021](/sites/default/files/styles/large/public/2021-11/13-EVVP9378-1500x.jpg?itok=FYVtY2J3)
Media Name
Structural steel is installed for the Highway 29 Dry Creek bridge realignment. | August 2021
Caption
Structural steel is installed for the Highway 29 Dry Creek bridge realignment. | August 2021
Media
Image
![Steel cross-bracing is installed between the Dry Creek bridge girders. | August 2021](/sites/default/files/styles/large/public/2021-11/14-EVVP9406-1500x.jpg?itok=eVw3w0sC)
Media Name
Steel cross-bracing is installed between the Dry Creek bridge girders. | August 2021
Caption
Steel cross-bracing is installed between the Dry Creek bridge girders. | August 2021
Media
Image
![Construction of the concrete piers for the Lynx Creek bridge along Highway 29. | August 2021](/sites/default/files/styles/large/public/2021-11/15-EVVP9353-1500x.jpg?itok=4Xi9_U8A)
Media Name
Construction of the concrete piers for the Lynx Creek bridge along Highway 29. | August 2021
Caption
Construction of the concrete piers for the Lynx Creek bridge along Highway 29. | August 2021
Media
Image
![Aerial view of the Hudson’s Hope shoreline protection berm. | August 2021](/sites/default/files/styles/large/public/2021-11/16-DJI_0642-Pano-1500x.jpg?itok=ysvWKirI)
Media Name
Aerial view of the Hudson’s Hope shoreline protection berm. | August 2021
Caption
Aerial view of the Hudson’s Hope shoreline protection berm. | August 2021
Media
Image
![An excavator at the bottom of the DA Thomas Road hill piles riprap on the Hudson’s Hope shoreline protection berm. | August 2021](/sites/default/files/styles/large/public/2021-11/17-DJI_0651-1500x.jpg?itok=uspLgK3U)
Media Name
An excavator at the bottom of the DA Thomas Road hill piles riprap on the Hudson’s Hope shoreline protection berm. | August 2021
Caption
An excavator at the bottom of the DA Thomas Road hill piles riprap on the Hudson’s Hope shoreline protection berm. | August 2021
Media
Image
![The middle section of Hudson’s Hope shoreline protection berm has a completed toe berm and fill and is ready for riprap placement. | August 2021](/sites/default/files/styles/large/public/2021-11/18-DJI_0638-1500x.jpg?itok=qkvdxr-i)
Media Name
The middle section of Hudson’s Hope shoreline protection berm has a completed toe berm and fill and is ready for riprap placement. | August 2021
Caption
The middle section of Hudson’s Hope shoreline protection berm has a completed toe berm and fill and is ready for riprap placement. | August 2021
Media
Image
![Glacial till is extracted at the 85th Avenue Industrial Lands and sent by conveyor belt to the dam site. | August 2021](/sites/default/files/styles/large/public/2021-11/01-STC_EV_DJI_0130-Pano-20210817-1500x.jpg?itok=siSEfUer)
Media Name
Glacial till is extracted at the 85th Avenue Industrial Lands and sent by conveyor belt to the dam site. | August 2021
Caption
Glacial till is extracted at the 85th Avenue Industrial Lands and sent by conveyor belt to the dam site. | August 2021
Media
Image
![Aerial view of the till conveyor and glacial till feeders. | August 2021](/sites/default/files/styles/large/public/2021-11/02-STC_EV_DJI_0110-20210817-1500x.jpg?itok=JxV8kYMA)
Media Name
Aerial view of the till conveyor and glacial till feeders. | August 2021
Caption
Aerial view of the till conveyor and glacial till feeders. | August 2021
Media
Image
![This mechanically stabilized earth wall is part of the updated conveyor loading system. Mine trucks drive on top to dump glacial till into the hopper. | August 2021](/sites/default/files/styles/large/public/2021-11/03-STC_EV_EVVP9560-20210817-1500x.jpg?itok=uTdfvXiF)
Media Name
This mechanically stabilized earth wall is part of the updated conveyor loading system. Mine trucks drive on top to dump glacial till into the hopper. | August 2021
Caption
This mechanically stabilized earth wall is part of the updated conveyor loading system. Mine trucks drive on top to dump glacial till into the hopper. | August 2021
Media
Image
![Shear pile work is happening on the Cache Creek bridge segment of the Highway 29 realignment. | August 2021](/sites/default/files/styles/large/public/2021-11/01-STC_EV_DJI_0339-20210820-1500x.jpg?itok=R0gqJypr)
Media Name
Shear pile work is happening on the Cache Creek bridge segment of the Highway 29 realignment. | August 2021
Caption
Shear pile work is happening on the Cache Creek bridge segment of the Highway 29 realignment. | August 2021
Media
Image
![Bridge concrete work progresses, following formwork removal at Cache Creek. | August 2021](/sites/default/files/styles/large/public/2021-11/02-STC_EV_DJI_0327-20210820-1500x.jpg?itok=KSsj-GzI)
Media Name
Bridge concrete work progresses, following formwork removal at Cache Creek. | August 2021
Caption
Bridge concrete work progresses, following formwork removal at Cache Creek. | August 2021
Media
Image
![Bridge pier construction at Farrell Creek. | August 2021](/sites/default/files/styles/large/public/2021-11/03-STC_EV_EVVP9791-20210820-1500x.jpg?itok=viMu-8KY)
Media Name
Bridge pier construction at Farrell Creek. | August 2021
Caption
Bridge pier construction at Farrell Creek. | August 2021
Media
Image
![This is a power cap construction platform for the Farrell Creek bridge. | August 2021](/sites/default/files/styles/large/public/2021-11/04-STC_EV_DJI_0280-20210820-1500x.jpg?itok=tDk83j0V)
Media Name
This is a power cap construction platform for the Farrell Creek bridge. | August 2021
Caption
This is a power cap construction platform for the Farrell Creek bridge. | August 2021
Media
Image
![This is a power cap construction platform for the Farrell Creek bridge. | August 2021](/sites/default/files/styles/large/public/2021-11/05-STC_EV_DJI_0262-20210820-1500x.jpg?itok=-7-KKYZn)
Media Name
This is a power cap construction platform for the Farrell Creek bridge. | August 2021
Caption
This is a power cap construction platform for the Farrell Creek bridge. | August 2021
Media
Image
![With the steel in place for the Dry Creek Highway 29 realignment, the next step is to install the precast concrete deck sections. | August 2021](/sites/default/files/styles/large/public/2021-11/06-STC_EV_DJI_0260-20210820-1500x.jpg?itok=GyDoLbL7)
Media Name
With the steel in place for the Dry Creek Highway 29 realignment, the next step is to install the precast concrete deck sections. | August 2021
Caption
With the steel in place for the Dry Creek Highway 29 realignment, the next step is to install the precast concrete deck sections. | August 2021
Media
Image
![The Lynx Creek Highway 29 realignment subgrade construction includes a detour and future highway embankment. | August 2021](/sites/default/files/styles/large/public/2021-11/07-STC_EV_DJI_0233-20210820-1500x.jpg?itok=6u5KDGSb)
Media Name
The Lynx Creek Highway 29 realignment subgrade construction includes a detour and future highway embankment. | August 2021
Caption
The Lynx Creek Highway 29 realignment subgrade construction includes a detour and future highway embankment. | August 2021
Media
Image
![The Lynx Creek Highway 29 realignment subgrade construction includes a detour and future highway embankment. | August 2021](/sites/default/files/styles/large/public/2021-11/08-STC_EV_DJI_0221-20210820-1500x.jpg?itok=tsHIAY6r)
Media Name
The Lynx Creek Highway 29 realignment subgrade construction includes a detour and future highway embankment. | August 2021
Caption
The Lynx Creek Highway 29 realignment subgrade construction includes a detour and future highway embankment. | August 2021
Media
Image
![Aerial view of the earthfill dam, approach channel and roller compacted concrete ramp, dam and core buttress, and powerhouse and spillways. | August 2021](/sites/default/files/styles/large/public/2021-11/06-20210825-DJI_0352-Pano-1500x.jpg?itok=I3m1ZjDZ)
Media Name
Aerial view of the earthfill dam, approach channel and roller compacted concrete ramp, dam and core buttress, and powerhouse and spillways. | August 2021
Caption
Aerial view of the earthfill dam, approach channel and roller compacted concrete ramp, dam and core buttress, and powerhouse and spillways. | August 2021
Media
Image
![The earthfill dam continues to take shape, with the generating station and spillways under construction in the background. | August 2021](/sites/default/files/styles/large/public/2021-11/07-20210825-EVVP9910-Pano-1500x_0.jpg?itok=A1oltkPt)
Media Name
The earthfill dam continues to take shape, with the generating station and spillways under construction in the background. | August 2021
Caption
The earthfill dam continues to take shape, with the generating station and spillways under construction in the background. | August 2021
Media
Image
![Penstock unit 4 is the last of the six penstock units to be constructed. | August 2021](/sites/default/files/styles/large/public/2021-11/10-20210826-EVVP0025-1500x.jpg?itok=0WVQMJj7)
Media Name
Penstock unit 4 is the last of the six penstock units to be constructed. | August 2021
Caption
Penstock unit 4 is the last of the six penstock units to be constructed. | August 2021
Media
Image
![The six Site C generating units are in varying stages of installation. | August 2021](/sites/default/files/styles/large/public/2021-11/01-20210826-EVVP9932-1500x.jpg?itok=lR-IMMiw)
Media Name
The six Site C generating units are in varying stages of installation. | August 2021
Caption
The six Site C generating units are in varying stages of installation. | August 2021
Media
Image
![Welding and spiral case installation on unit 2 in the powerhouse. | August 2021](/sites/default/files/styles/large/public/2021-11/02-20210826-EVVP9938-1500x.jpg?itok=oNDxq10X)
Media Name
Welding and spiral case installation on unit 2 in the powerhouse. | August 2021
Caption
Welding and spiral case installation on unit 2 in the powerhouse. | August 2021
Media
Image
![Installation of spiral case segments on unit 3 in the powerhouse. | August 2021](/sites/default/files/styles/large/public/2021-11/03-20210826-EVVP9950-1500x.jpg?itok=00tWutTC)
Media Name
Installation of spiral case segments on unit 3 in the powerhouse. | August 2021
Caption
Installation of spiral case segments on unit 3 in the powerhouse. | August 2021
Media
Image
![Installation of the lower pit liner and thrust section on unit 4 in the powerhouse. | August 2021](/sites/default/files/styles/large/public/2021-11/04-20210826-EVVP9955-1500x.jpg?itok=WVyGPOpg)
Media Name
Installation of the lower pit liner and thrust section on unit 4 in the powerhouse. | August 2021
Caption
Installation of the lower pit liner and thrust section on unit 4 in the powerhouse. | August 2021
Media
Image
![Embedding the draft tube elbow on unit 5 in the powerhouse. | August 2021](/sites/default/files/styles/large/public/2021-11/05-20210826-EVVP9959-1500x.jpg?itok=6OLm32NG)
Media Name
Embedding the draft tube elbow on unit 5 in the powerhouse. | August 2021
Caption
Embedding the draft tube elbow on unit 5 in the powerhouse. | August 2021
Media
Image
![Preparing to install the draft tube liner on unit 6 in the powerhouse. | August 2021](/sites/default/files/styles/large/public/2021-11/06-20210826-EVVP9966-1500x.jpg?itok=-LADxCtm)
Media Name
Preparing to install the draft tube liner on unit 6 in the powerhouse. | August 2021
Caption
Preparing to install the draft tube liner on unit 6 in the powerhouse. | August 2021
Media
Image
![Installation of the working platform and formwork at the Cache Creek bridge for the Highway 29 realignment. | August 2021](/sites/default/files/styles/large/public/2022-02/01-STC_EV_EVVP0156-20210827-1500x.jpg?itok=u773cLha)
Media Name
Installation of the working platform and formwork at the Cache Creek bridge for the Highway 29 realignment. | August 2021
Caption
Installation of the working platform and formwork at the Cache Creek bridge for the Highway 29 realignment. | August 2021
Media
Image
![Installation of the working platform and formwork at the Cache Creek bridge for the Highway 29 realignment. | August 2021](/sites/default/files/styles/large/public/2021-11/02-STC_EV_EVVP0133-20210827-1500x.jpg?itok=mOBjW0Ur)
Media Name
Installation of the working platform and formwork at the Cache Creek bridge for the Highway 29 realignment. | August 2021
Caption
Installation of the working platform and formwork at the Cache Creek bridge for the Highway 29 realignment. | August 2021
Media
Image
![View of the embankment at the Lynx Creek segment on Highway 29. | August 2021](/sites/default/files/styles/large/public/2021-11/03-STC_EV_DJI_0406-20210827-1500x.jpg?itok=vY7DBE0p)
Media Name
View of the embankment at the Lynx Creek segment on Highway 29. | August 2021
Caption
View of the embankment at the Lynx Creek segment on Highway 29. | August 2021
Media
Image
![View of the embankment at the Lynx Creek segment on Highway 29. | August 2021](/sites/default/files/styles/large/public/2021-11/04-STC_EV_DJI_0367-20210827-1500x.jpg?itok=OVld9yWU)
Media Name
View of the embankment at the Lynx Creek segment on Highway 29. | August 2021
Caption
View of the embankment at the Lynx Creek segment on Highway 29. | August 2021
Media
Image
![View of Lynx Creek bridge construction and rip-rap stockpile. | August 2021](/sites/default/files/styles/large/public/2021-11/05-STC_EV_DJI_0404-Pano-20210827-1500x.jpg?itok=KEdXP6oG)
Order
5.00