The transmission and substation components of the Site C project will be procured through multiple contracts, including existing BC Hydro blanket contracts and agreements.
The components include: a new substation at the Site C dam, two new 75-kilometre, 500 kV transmission lines from the Site C substation to the Peace Canyon substation, and the expansion of the Peace Canyon substation to enable connection of the new transmission lines.
Transmission Line: Construction
Two new 500 kV transmission lines will be built from Site C to the Peace Canyon generating station over a distance of approximately 75 kilometres. The lines will be located along an existing transmission right-of-way.
The scope of this contract includes:
- Construction of temporary access roads;
- Preparation of tower sites;
- Supply and installation of tower foundations;
- Assembly and erection of towers; and
- Conductor stringing.
Contractor | Contract award date | Construction timeline (subject to change) |
---|---|---|
Allteck Line Contractors Inc. | May 2018 | 2018–2023 |
Transmission Line: Supply of Lattice Towers
- Detailing of lattice tower structures;
- Test assembly and load testing of newly designed towers as required; and,
- Manufacture and supply of lattice tower structures, including fasteners.
Contractor | Contract award date | Construction timeline (subject to change) |
---|---|---|
SA-RA Energy, Construction, Trade & Industry Inc. | May 2017 | Supplied from 2017–2019 |
Transmission Line: Supply of Conductors
- Manufacture and supply of ACSR and ASC conductors.
Contractor | Contract award date | Construction timeline (subject to change) |
---|---|---|
Nexans Canada Inc. | February 2018 | Supplied from 2018–2019 |
Transmission Line: Supply and Delivery of Grillage Foundations
The contract includes the manufacture, supply and delivery of steel grillage foundations.
Contractor | Contract award date | Construction timeline (subject to change) |
---|---|---|
Locweld Inc. | April 2017 | Supplied in 2017–2018 |
Transmission Line: Peace Canyon 500kV GIS Expansion
The scope of the contract is to expand the existing Peace Canyon 500kV gas-insulated substation and includes:
- Construction of an outdoor switchyard adjacent to the existing GIS building; and,
- Expansion of the existing 500 kV gas-insulated switchgear inside the GIS building.
- Design, manufacture and testing of 500kV GIS equipment.
Contractor | Contract award date | Construction timeline (subject to change) |
---|---|---|
ABB Inc. | July 2017 | 2018–2019 |
Site C Substation: Design and Supply of 500 kV Shunt Reactor
This contract includes the design, supply and manufacture of one 500 kV, 135 MVAR shunt reactor.
Contractor | Contract award date | Construction timeline (subject to change) |
---|---|---|
Siemens Canada Ltd. | February 2017 | Supplied in 2019 |
Site C Substation: Supply and Installation of Pre-Fabricated Control Building
This contract includes the design, supply and installation of the control building for the Site C substation.
Contractor | Contract award date | Construction timeline (subject to change) |
---|---|---|
Empirica Infrastructure Inc. | March 2017 | Supplied in 2018 |
Site C Substation: Construction
A single construction contract has been issued for both the 500 kV and 138 kV switchyards, which includes:
- Civil works including fencing, foundations, roads, oil containment and crushed rock surfacing.
- Fit-out of a pre-fabricated control building.
- Supply and installation of a storage building.
- Electrical work including steel erection, buswork, power and control cables, grounding, lighting and equipment assembly and installation.
- Installation of protection and control equipment.
- Installation of telecommunication equipment and tower.
Contractor | Contract award date | Construction timeline (subject to change) |
---|---|---|
F&M Installations | February 2018 | 2018–2020 |
Site C Substation: Supply of 550 kV Disconnect Switches
This contract includes the design, supply, testing and delivery of 550 kV disconnect switches for the Site C substation.
Contractor | Contract award date | Construction timeline (subject to change) |
---|---|---|
Mindcore Technologies | March 2017 | Supplied in 2018 |
Procurement Information
Contract Award
| |
---|---|
June 20, 2018
|
|
B.C.-based company awarded contract to build Site C transmission line For business and job opportunities, please email: careers@allteck.ca or visit www.allteck.ca/careers. |
Additional Information
- Transmission and Substation Fact Sheet PDF • 129.02 KB