File Name
Offices and worker accommodation lodge. (February 2016)
File Alt
Offices and worker accommodation lodge. (February 2016)
File Name
In-river excavation. (February 2016)
File Alt
In-river excavation. (February 2016)
File Name
In-river excavation. (February 2016)
File Alt
In-river excavation. (February 2016)
File Name
In-river excavation. (February 2016)
File Alt
In-river excavation. (February 2016)
File
File Name
River Road construction. (February 2016)
File Alt
River Road construction. (February 2016)
File Name
River Road rip-rap placement. (February 2016)
File Alt
River Road rip-rap placement. (February 2016)
File Name
Temporary construction access bridge. (February 2016)
File Alt
Temporary construction access bridge. (February 2016)
File Name
Temporary construction access bridge. (February 2016)
File Alt
Temporary construction access bridge. (February 2016)
File Name
Three tiers of end block of worker accommodation lodge. (February 2016)
File Alt
Three tiers of end block of worker accommodation lodge. (February 2016)
File
File Name
View of gymnasium at worker accommodation lodge. (February 2016)
File Alt
View of gymnasium at worker accommodation lodge. (February 2016)
File Name
Water delivery of water for water tank at site of worker accommodation lodge. (February 2016)
File Alt
First water delivery of water for water tank at site of worker accommodation lodge. (February 2016)
File Name
Purlins for the ceiling of the gymnasium. (February 2016)
File Alt
Purlins for the ceiling of the gymnasium. (February 2016)
File Name
Excavator unloading culvert sections. (February 2016)
File Name
Installation of security trailers. (February 2016)
File Name
Aerial view worker accommodation. (February 2016)
File Alt
Temporary Construction Bridge
File Name
The 329-metre-long bridge built for transporting people, machinery and materials across the Peace River. (March 2016)
File Alt
Bridge
File
File Name
Trucks hauling material. (March 2016)
File Alt
Trucks hauling material. (March 2016)
File
File Name
Machinery and equipment mobilization for the main civil works contractor. (April 2016)
File Alt
Machinery and equipment mobilization for the main civil works contractor. (April 2016)
File
File Name
Machinery and equipment mobilization for the main civil works contractor. (April 2016)
File Alt
Machinery and equipment mobilization for the main civil works contractor. (April 2016)
File
File Name
Work continues on the worker accommodation lodge. (April 2016)
File Alt
Work continues on the worker accommodation lodge. (April 2016)
File
File Name
Coconut matting around the site to protect from erosion and sloughing. (April 2016)
File Alt
Coconut matting around the site to protect from erosion and sloughing. (April 2016)
File
File Name
Work is underway to build the site drainage. (April 2016)
File Alt
Work is underway to build the site drainage. (April 2016)
File Name
South facing view from the north bank looking down on the access bridge. (April 2016)
File Alt
South facing view from the north bank looking down on the access bridge. (April 2016)
File Name
Work on potable water pipe. (April 2016)
File Alt
Work on potable water pipe. (April 2016)
File Name
Peace River Hydro Partners continue preparatory work and equipment mobilization on the south bank. (May 2016)
File Alt
Peace River Hydro Partners continue preparatory work and equipment mobilization on the south bank. (May 2016)
File Name
Peace River Hydro Partners continue preparatory work and equipment mobilization on the south bank. (May 2016)
File Alt
Peace River Hydro Partners continue preparatory work and equipment mobilization on the south bank. (May 2016)
File Name
Peace River Hydro Partners continue to mobilize equipment to the dam site area. (May 2016)
File Alt
Peace River Hydro Partners continue to mobilize equipment to the dam site area. (May 2016)
File Name
Peace River Hydro Partners continue preparatory work and equipment mobilization on the south bank. (May 2016)
File Alt
Peace River Hydro Partners continue preparatory work and equipment mobilization on the south bank. (May 2016)
File Name
Workers cover the new drainage pipes along Old Fort Road. (May 2016)
File Alt
Workers cover the new drainage pipes along Old Fort Road. (May 2016)
File Name
Placing rip-rap on River Road. (May 2016)
File Alt
Placing rip-rap on River Road. (May 2016)
File Name
View of temporary construction bridge from North Bank Road. (May 2016)
File Alt
View of temporary construction bridge from North Bank Road. (May 2016)
File
File Name
May 2016 - Upgrading continues on 240 Road.
File Alt
May 2016 - Upgrading continues on 240 Road.
File Name
June 2016 - Upgrading continues on 240 Road.
File Alt
June 2016 - Upgrading continues on 240 Road.
File
File Name
View of Septimus Road looking south. (May 2016)
File Alt
View of Septimus Road looking south. (May 2016)
File Name
Logging trucks hauling timber from the dam site on the temporary construction access bridge. (May 2016)
File Alt
Logging trucks hauling timber from the dam site on the temporary construction access bridge. (May 2016)
File Name
Aerial view of north bank of dam site showing the worker accommodation lodge. (July 2016)
File Alt
Worker accomodation lodge at north bank
File Name
Aerial view of north bank of dam site showing the worker accommodation lodge. (July 2016)
File Alt
Worker accomodation lodge north bank areal shot
File Name
Aerial view of south bank of dam site showing the temporary Peace River construction bridge. (July 2016)
File Alt
Temporary bridge south bank
File Name
Aerial view of north bank of dam site showing River Road riprap placement. (July 2016)
File Alt
North bank riprap placement
File Name
Peace River Hydro Partners continue equipment mobilization including this Atlas Copco MT2010. (August 2016)
File Name
Peace River Hydro Partners continue equipment mobilization including this Merlo Roto 40.18s Rotary Telehander with manbasket, forks and bucket. (August 2016)
File Name
Peace River Hydro Partners continue equipment mobilization including this Boltec MC. (July 2016)
File Name
Peace River Hydro Partners continue equipment mobilization including this Putzmeister Sika 500. (July 2016)
File Name
Peace River Hydro Partners continue equipment mobilization including this Antraquip AQ150 Roadheader. (July 2016)
File Name
Concrete pour on the south bank. (July 2016)
File Name
Concrete pour on the south bank. (July 2016)
File Name
The south bank batch plant, installed by Peace River Hydro Partners, will be used in the construction of the roller compacted concrete buttress (i.e., foundation) for the generating station and spillways. (September 2016)
File Alt
The south bank batch plant, installed by Peace River Hydro Partners, will be used in the construction of the roller compacted concrete buttress (i.e., foundation) for the generating station and spillways. (September 2016)
File Name
Construction of south bank access roads. (September 2016)
File Alt
Construction of south bank access roads. (September 2016)
File Name
Construction of south bank access roads. (September 2016)
File Alt
Construction of south bank access roads. (September 2016)
File Name
Work continues to build the south bank cofferdam. (September 2016)
File Alt
Work continues to build the south bank cofferdam. (September 2016)
File Name
Work continues to build the south bank cofferdam. (September 2016)
File Alt
Work continues to build the south bank cofferdam. (September 2016)
File Name
Work continues to build the south bank cofferdam. (September 2016)
File Alt
Work continues to build the south bank cofferdam. (September 2016)
File Name
Looking north at construction of the south bank cofferdam. (September 2016)
File Alt
Looking north at construction of the south bank cofferdam. (September 2016)
File Name
Work continues to build the south bank cofferdam. (September 2016)
File Alt
Work continues to build the south bank cofferdam. (September 2016)
File Name
Drilling and installation of geotechnical instrumentation on the south bank. (September 2016)
File Alt
Drilling and installation of geotechnical instrumentation on the south bank. (September 2016)
File Name
South bank construction activities. (September 2016)
File Alt
South bank construction activities. (September 2016)
File Name
Offices and worker accommodation lodge. (February 2016)
File Alt
Offices and worker accommodation lodge. (February 2016)
File Name
Completed worker accommodation lodge, looking west. (October 2016)
File Alt
Completed worker accommodation lodge, looking west. (October 2016)
File Name
View of north bank access roads. (October 2016)
File Alt
View of north bank access roads. (October 2016)
File Name
Completed worker accommodation lodge. (October 2016)
File Alt
Completed worker accommodation lodge. (October 2016)
File Name
Construction activities on the north and south banks. (October 2016)
File Alt
Construction activities on the north and south banks. (October 2016)
File Name
River Road downstream of dam site. (October 2016)
File Alt
River Road downstream of dam site. (October 2016)
File Name
Temporary Peace River construction bridge in use. (October 2016)
File Alt
Temporary Peace River construction bridge in use. (October 2016)
File Name
View of the south bank construction work, facing the north bank. (October 2016)
File Alt
View of the south bank construction work, facing the north bank. (October 2016)
File Name
View of the south bank construction work, looking west. (October 2016)
File Alt
View of the south bank construction work, looking west. (October 2016)
File Name
South bank work area including concrete batch plants. (October 2016)
File Alt
South bank work area including concrete batch plants. (October 2016)
File Name
Old Fort Road realignment. (October 2016)
File Alt
Old Fort Road realignment. (October 2016)
File Name
Construction of a storage area for relocated excavated material on the north bank of the dam site, upstream from the Peace River construction bridge. (October 2016)
File Alt
Construction of a storage area for relocated excavated material on the north bank of the dam site, upstream from the Peace River construction bridge. (October 2016)
File Name
Dust mitigation on the north bank view point access road. (October 2016)
File Alt
Dust mitigation on the north bank view point access road. (October 2016)
File Name
Construction of a fill area along the north bank road. (October 2016)
File Alt
Construction of a fill area along the north bank road. (October 2016)
File Name
Construction of the Moberly River construction bridge, looking northeast. (October 2016)
File Alt
Construction of the Moberly River construction bridge, looking northeast. (October 2016)
File Name
Construction of the Moberly River construction bridge, looking southeast. (October 2016)
File Alt
Construction of the Moberly River construction bridge, looking southeast. (October 2016)
File Name
Construction continues on a storage area for relocated excavated material, with right bank cofferdam construction in the background. (October 2016)
File Alt
Construction continues on a storage area for relocated excavated material, with right bank cofferdam construction in the background. (October 2016)
File Name
Looking upstream at the causeway for a storage area for relocated excavated material on the north bank. (November 2016)
File Alt
Looking upstream at the causeway for a storage area for relocated excavated material on the north bank. (November 2016)
File Name
View of the north bank, looking downstream above a storage area for relocated excavated material. (November 2016)
File Alt
View of the north bank, looking downstream above a storage area for relocated excavated material. (November 2016)
File Name
Concrete batch plants at night. (November 2016)
File Alt
Concrete batch plants at night. (November 2016)
File Name
Concrete batch plants on the south bank. (November 2016)
File Alt
Concrete batch plants on the south bank. (November 2016)
File Name
Aggregate production area. This aggregate will be used to produce roller-compacted concrete. (November 2016)
File Alt
Aggregate production area. This aggregate will be used to produce roller-compacted concrete. (November 2016)
File Name
Aggregate production area on the south bank. (November 2016)
File Alt
Aggregate production area on the south bank. (November 2016)
File Name
Construction continues on the Moberly River Construction Bridge. (November 2016)
File Alt
Construction continues on the Moberly River Construction Bridge. (November 2016)
File Name
Aerial view of the stage 1 right bank cofferdam, including one of three slurry (concrete) production plants. (November 2016)
File Alt
Aerial view of the stage 1 right bank cofferdam, including one of three slurry (concrete) production plants. (November 2016)
File Name
Riprap placement on the south bank. (December 2016)
File Alt
Riprap placement on the south bank. (December 2016)
File Name
Crews preparing to apply shotcrete to the drainage tunnel on the south bank. (December 2016)
File Alt
Crews preparing to apply shotcrete to the drainage tunnel on the south bank. (December 2016)
File Name
Shotcrete application at the drainage tunnel on the south bank. (December 2016)
File Alt
Shotcrete application at the drainage tunnel on the south bank. (December 2016)